Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
Project | Original Estimated Total Cost |
Revised Estimated Total Cost |
Actual Total Cost to Date |
Main Estimates 2012–13 |
Planned Spending 2012–13 |
Total Authorities 2012–13 |
Actual 2012–2013 |
Expected date of close-out |
---|---|---|---|---|---|---|---|---|
Notes:
|
||||||||
Real Property Services | ||||||||
Workspace Renewal Project (PPA) See Status Report on Projects Operating note 1 * | 54,000 | 54,000 | 2,838 | 0 | 2,110 | 2,110 | 1,876 | 2016 |
Management of Information Technology | ||||||||
Human Resource Business Solution Pilot (EPA) See Status Report on Projects Operating note 2 ** | 13,189 | 13,189 | 8,927 | 0 | 6,740 | 8,240 | 6,021 | 2014 |
Human Resource Data Interoperability (PPA) | 2,960 | 2,960 | 586 | 0 | 0 | 600 | 586 | 2014 |