Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
PPTO-PS-003 Project Tracking and Oversight Process
January 2000
Chief Information Officer Branch
Treasury Board of Canada Secretariat
The purpose of this document is to describe the process to be followed by a project manager to track a project.
This process is applicable to any Information Management/Information Technology (IM/IT) project and to any phase of the IM/IT development life cycle.
Everyone in the organisation has a role to perform in this process.
Role | Description/Responsibilities |
Project Leader (PL) | This is the person appointed by the sponsoring department to be accountable for all external and internal aspects of a capital project. http://www.tbs-sct.gc.ca/pubs_pol/dcgpubs/TBM_122/abkglos-eng.asp |
Project Manager (PM) | This is a person formally appointed to manage a project with specific accountability for achieving defined project objectives within allocated resources. A project manager has access to, and a formally defined relationship with, the project leader to which the specific project has been assigned. http://www.tbs-sct.gc.ca/ pubs_pol/dcgpubs/TBM_122/abkglos-eng.asp |
Project Team Member (PTM) |
Software engineer or writer assigned to a project
Responsible for completing project tasks, providing input to plans, and providing status |
Project Management Office (PMO) | This is a distinct and temporary organisational unit led by the project manager tasked to administer a project. It consists of assigned full or part-time members of the sponsoring department and, when appropriate, representatives of participating departments working together in accordance with any interdepartmental agreements or memorandums of
understanding. http://www.tbs-sct.gc.ca/ pubs_pol/dcgpubs/TBM_122/abkglos-eng.asp |
Quality Assurance (QA) | Responsible for support of quality assurance activities. |
Configuration Management (CM) | Responsible for support of configuration management activities. |
Refer to Enhanced Management Framework Lexicon.
Refer to Enhanced Management Framework Acronyms.
Refer to Enhanced Management Framework Web Links
This process was designed to satisfy the SEI Software Capability Maturity Model goals for Level 2 Key Practice: Software Project Tracking and Oversight.
Treasury Board Secretariat Policies:
The policies above are located at the following URL:
http://www.tbs-sct.gc.ca/pubs_pol/dcgpubs/TBM_122/siglist-eng.asp
Annex A - Flowcharting Symbols
PPTO-PS-001 Project Management Process
PPTO-PS-002 Project Planning Process
PEER-PS-001 Peer Review Process
PPTO-PD-001 Estimate Software Product Size Basic Procedure
PPTO-PD-002 Estimate Project Resources/Schedule Basic Procedure
EMF Business Case Guideline
PPTO-TM-001 Process/Procedure Template
PPTO-TM-002 Project Plan Template
PPTO-TM-003 Project Estimates Template
EMF Project Charter Template
PPTO-CK-001 Project Management Checklist
The following entry criteria describes the input's state, an event, or an expired amount of time, which is required before this process can begin.
Details of Entry Criteria |
|
The overall process flow given below shows the interaction and flow among the activities. More details about the activities can be found in 2.4 Activities.
The following inputs are used in this process. Where they don't exist, identify any associated risks.
Input | Detail of Inputs and remarks | Ref. |
Project Plan |
|
PPTO-TM-002 |
Project Actuals |
|
The following activities are performed in this process. Document all assumptions, risks, constraints etc. in the Project Plan.
No. | Activities | Action by | Detail of Activities and Remarks | Ref. |
1 | - Project Planning | PM | - Project planning in the context of overall project management is documented in the referenced documents. |
PPTO-PS-002
PPTO-PS-001 |
2 | - Obtain Tracking Requirements | PM | - Obtain the data collection requirements for project tracking from the Project Plan. |
PPTO-PS-002
PPTO-PS-001 PPTO-TM-002 |
3 | - Obtain Baseline | PM | - Obtain the baselined estimates from the Project Plan. |
PPTO-PS-002
PPTO-PS-001 PPTO-TM-002 |
4 |
- Collect Actuals
- Compare Actuals to Plans |
PM |
- Collect and store the current actual values of the tracking data, and compare them to the baselined estimates.
- Perform according to Project Plan Schedule. |
PPTO-PS-002
PPTO-PS-001 PPTO-TM-002 |
5 |
- Evaluate Status and Performance
- Monitor Risks |
PM | - Evaluate the project's performance and status relative to the plan. Identify the reasons for deviations from the plan; identify both delays and accelerations; and monitor risks. |
PPTO-PS-002
PPTO-PS-001 PPTO-TM-002 |
6 |
- Status Meeting
- Project Review - Commitment Review |
- Determine whether the project's objectives, plan, or resources need to be adjusted.
- Re-planning Needed? - [Yes] Go to activity 1. - [No] Is project completed? - [Yes] Write postmortem. - [No] Go to activity 4. |
PPTO-PS-002
PPTO-PS-001 |
The following outputs are produced or modified by the activities in this process.
Output | Detail of Outputs and Remarks | Ref. |
Project Logs and Status Report |
- Update issue log, decision log, action log and risk log.
- Document:
- Reasons for deviations from the plan
- Corrective actions taken - Recommendations for further adjustments - Track and report on requirement changes, size, schedule, cost, quality, people and resources such as equipment, tool, training, development environments, infrastructure, as defined in the Project Plan. - Assess and document status as per the schedule and reporting requirements defined in the Project Plan. - Store the logs and status reports in the project's quality records to form part of the projects historical data. |
|
Project Postmortem | - Conduct a postmortem to capture lessons learned. |
Output Validation |
To determine if the outputs are within specification,
- Use the (PEER-PS-001) Peer Review Process and any techniques described in your IM/IT methodology. - Use validation techniques referred to in your IM\IT methodology such as testing, demonstration, analysis and inspection. |
Details of Exit Criteria |
|
Refer to Enhanced Management Framework, Exposure Draft Executive Toolkit, November 22, 1999 for the Project Health Check Dashboard.
Not applicable at this time. Populate table if seeking ISO certification. For more information, refer to (PPTO-TM-001) Process/Procedure Template.
Description (no. and name) |
Storage Location | Filing / Index | Minimum Storage Period |
Not applicable at this time. Populate if seeking ISO certification. For more information, refer to (PPTO-TM-001) Process/Procedure Template.
Number | Name | Revision Date (or version) |
Owner |
Refer to the Enhanced Management Framework Lexicon or insert a reference to your organisation's Lexicon.
Refer to the Enhanced Management Framework Acronyms or insert a reference to your organisation's Acronyms.
![]() |
|
Parallelogram represent inputs and outputs to or from a process/procedure. | |
![]() |
![]() |
Rectangles represent individual process/procedure activities. | Diamonds represent important decision points in the process/procedure. |
![]() |
![]() |
Lines with arrowheads connect symbols to show the progression or direction of the activities. | Circles represent connectors when a process/procedure flowchart continues on the next page. |
Caputo, Kim, CMM Implementation Guide: Choreographing Software Process Improvement. Addison Wesley, Reading, Massachusetts, 1998.
Refer to Enhanced Management Framework Web Links.
Revision Number | Date of Issue | Author(s) | Brief Description of Change |
0.1 | 1999-09-23 | EMF/PPTO | Draft 0.1 |
1.0 | 1999-11-09 | EMF/PPTO | First Draft |
1.0 | 2000-01-13 | EMF/PPTO | Second Draft |