Results by Site Impact
Change results view to: Name and Location Contaminants and Media
FCSI Identifier Site Name |
Status | Fiscal Year | Classification | Highest Step Completed |
---|---|---|---|---|
00000430
682 - Tahltan - 07655 - TELEGRAPH CREEK 6 - 7000023894 |
Historical review planned. | 2023-2024 | 01 Identify Suspect Sites | |
00000545
530 - Witset First Nation - 06748 - MORICETOWN 1 - 0902240305 |
Detailed testing completed. Remediation / risk management planned. | 2023-2024 | I Insufficient Information | 05 Detailed Testing Program |
00000546
530 - Witset First Nation - 06751 - BABINE 17 - 0902240405 |
Detailed testing completed. Remediation / risk management planned. | 2023-2024 | I Insufficient Information | 05 Detailed Testing Program |
00000547
530 - Witset First Nation - 06749 - CORYATSAQUA (MORICETOWN) 2 - 0902240505 |
Detailed testing completed. Remediation / risk management planned. | 2023-2024 | I Insufficient Information | 05 Detailed Testing Program |
00000551
670 - Skidegate - 07690 - SKIDEGATE 1 - 0902242405 |
Detailed testing completed. Remediation / risk management planned. | 2023-2024 | I Insufficient Information | 05 Detailed Testing Program |
00000553
670 - Skidegate - 07690 - SKIDEGATE 1 - 0902244405 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00000555
669 - Old Massett Village Council - 07664 - MASSET 1 - 0902244605 |
Historical review completed. Initial testing underway. | 2023-2024 | 02 Historical Review | |
00000557
530 - Witset First Nation - 06749 - CORYATSAQUA (MORICETOWN) 2 - 0902244805 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00002452
Former Storage Tank |
Historical review completed. No further action required. | 2009-2010 | 02 Historical Review | |
00002909
TUYA RIVER NEAR TELEGRAPH CREEK |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00002913
SURPRISE CREEK NEAR THE MOUTH |
Confirmatory sampling completed. No further action required. | 2023-2024 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00002934
TWO MILE CREEK IN DISTRICT LOT 4834 |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00002935
SKEENA RIVER AT USK |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00002938
EXCHAMSIKS RIVER NEAR TERRACE |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00002939
KLOIYA RIVER NEAR PRINCE RUPERT |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00002952
HIRSCH CREEK NEAR THE MOUTH |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00006208
670 - Skidegate - 07690 - SKIDEGATE NO. 1 - 7000029494 |
Initial testing completed. No further action required. | 2000-2001 | I Insufficient Information | 03 Initial Testing Program |
00006218
682 - Tahltan - 07658 - DEASE LAKE 9 - 7000023794 |
Historical review planned. | 2023-2024 | 01 Identify Suspect Sites | |
00006277
682 - Tahltan - 09034 - GUHTHE TAH NO. 12 - 7000101598 |
Confirmatory sampling completed. No further action required. | 2008-2009 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00006278
530 - Witset First Nation - 06751 - BABINE 17 - 7000103998 |
Detailed testing completed. Remediation / risk management planned. | 2023-2024 | I Insufficient Information | 05 Detailed Testing Program |
00006288
680 - Kitselas - 07644 - KULSPAI 6 - 7000120598 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00006324
676 - Haisla Nation - 07620 - KITAMAAT 2 - 7000105598 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00006354
669 - Old Massett Village Council - 07664 - MASSET 1 - 7000030194 |
Historical review completed. Initial testing underway. | 2023-2024 | 02 Historical Review | |
00006404
531 - Gitanmaax - 06755 - GITANMAAX 1 - 7000099898 |
Detailed testing completed. Remediation / risk management planned. | 2023-2024 | 1 High Priority for Action | 05 Detailed Testing Program |
00006405
535 - Gitsegukla - 06772 - GITSEGUKLA 1 - 7000100898 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00006407
530 - Witset First Nation - 06748 - MORICETOWN 1 - 7000103698 |
Detailed testing completed. Remediation / risk management planned. | 2023-2024 | I Insufficient Information | 05 Detailed Testing Program |
00006408
530 - Witset First Nation - 06751 - BABINE 17 - 7000103898 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00006409
676 - Haisla Nation - 07620 - KITAMAAT 2 - 7000105698 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00006438
537 - Gitanyow - 06782 - GITANYOW 1 - 7000099498 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00006448
682 - Tahltan - 09034 - GUHTHE TAH 12 - 7000101698 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00006459
676 - Haisla Nation - 07620 - KITAMAAT 2 - 7000040194 |
Historical review completed. Initial testing underway. | 2023-2024 | 02 Historical Review | |
00006463
678 - Nisga'a Village of Laxgalt'sap - 07611 - LACHKALTSAP 9 - 7000023594 |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00006473
682 - Tahltan - 07658 - DEASE LAKE NO. 9 - 7000102098 |
Confirmatory sampling completed. No further action required. | 2008-2009 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00006475
530 - Witset First Nation - 06748 - MORICETOWN 1 - 7000103798 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00006476
533 - Glen Vowell - 06760 - SIK-E-DAKH 2 - 7000108698 |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | N Not a Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00006489
531 - Gitanmaax - 06755 - GITANMAAX NO. 1 - 7000099698 |
Confirmatory sampling completed. No further action required. | 2009-2010 | I Insufficient Information | 09 Confirmatory Sampling and Final Reporting |
00006490
537 - Gitanyow - 06782 - GITANYOW 1 / 7000100498 |
Historical review completed. No further action required. | 2023-2024 | 02 Historical Review | |
00006498
682 - Tahltan - 07655 - TELEGRAPH CREEK NO. 6 - 0902034105 |
Detailed testing completed. No further action required. | 2008-2009 | 1 High Priority for Action | 05 Detailed Testing Program |
00006515
535 - Gitsegukla - 06772 - GITSEGUKLA 1 - 7000100198 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00006530
531 - Gitanmaax - 06755 - GITANMAAX 1 - 7000099998 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00006531
533 - Glen Vowell - 06760 - SIK-E-DAKH 2 - 7000108998 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00006540
537 - Gitanyow - 06782 - GITANYOW 1 - 7000099398 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00006541
535 - Gitsegukla - 06772 - GITSEGUKLA 1 - 7000100398 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00006543
530 - Moricetown - 06748 - MORICETOWN NO. 1 - 7000103198 |
Confirmatory sampling completed. No further action required. | 2009-2010 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00006544
678 - Nisga'a Village of Laxgalt'sap - 07611 - LACHKALTSAP NO. 9 - 7000104598 |
Confirmatory sampling completed. No further action required. | 2010-2011 | I Insufficient Information | 09 Confirmatory Sampling and Final Reporting |
00006545
676 - Haisla Nation - 07620 - KITAMAAT 2 - 7000105498 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00006572
535 - Gitsegukla - 06772 - GITSEGUKLA 1 - 7000100298 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00006586
535 - Gitsegukla - 06772 - GITSEGUKLA 1 - 7000100698 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00006591
530 - Witset First Nation - 06748 - MORICETOWN 1 - 7000103398 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00006593
530 - Witset First Nation - 06748 - MORICETOWN 1 - 7000103598 |
Detailed testing completed. Remediation / risk management planned. | 2023-2024 | I Insufficient Information | 05 Detailed Testing Program |
00006594
535 - Gitsegukla - 06772 - GITSEGUKLA 1 - 7000100998 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00006766
536 - Gitwangak - 06776 - GITWANGAK 2 - 0903020906 |
Historical review planned. | 2023-2024 | 01 Identify Suspect Sites | |
00006813
671 - Nisga'a Village of Gingolx - 07705 - KINCOLITH NO. 14 - 7000110298 |
Confirmatory sampling completed. No further action required. | 2006-2007 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00006909
679 - Nisga'a Village of Gitwinksihlkw - 07614 - ZAULZAP 29 - 0903290807 |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00006912
671 - Nisga'a Village of Gingolx - 07705 - KINCOLITH NO. 14 - 0903296807 |
Detailed testing completed. No further action required. | 2010-2011 | 2 Medium Priority for Action | 05 Detailed Testing Program |
00006933
540 - Kitasoo Xai'xais Nation - 07886 - KITASOO 1 - 0903376808 |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00007576
531 - Gitanmaax - 06755 - GITANMAAX 1 / 0904113609 |
Historical review completed. No further action required. | 2012-2013 | 02 Historical Review | |
00007674
678 - Nisga'a Village of Laxgalt'sap - 07611 - LACHKALTSAP 9 - 0904385609 |
Long term monitoring completed. No further action required. | 2017-2018 | N Not a Priority for Action | 10 Long-Term Monitoring (Optional) |
00007677
674 - Lax Kw'alaams - 07770 - LAX KW'ALAAMS 1 - 0904391809 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 1 High Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00007761
676 - Haisla Nation - 07619 - KITAMAAT 1 - 0904607609 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 1 High Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00008201
540 - Kitasoo Xai'xais Nation - 07886 - KITASOO 1 - BC04825611 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00008204
540 - Kitasoo Xai'xais Nation - 07886 - KITASOO 1 - BC04825911 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00011584
NASS RIVER ABOVE SHUMAL CREEK |
Historical review completed. No further action required. | 2012-2013 | 02 Historical Review | |
00019562
Cumshewa |
Initial testing completed. No further action required. | 2015-2016 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00020171
Prince Rupert, Seal Cove, and Prince Rupert MCTS - Past Fuel Storage |
Initial testing completed. No further action required. | 2009-2010 | 03 Initial Testing Program | |
00020173
Prince Rupert, Seal Cove, and Prince Rupert MCTS - Wharf and Loading Facilities |
Initial testing completed. No further action required. | 2009-2010 | 03 Initial Testing Program | |
00020345
McCoy Cove - Sector Light |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00020354
Striae Islands |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00020755
Rose Inlet |
Initial testing completed. Detailed testing underway. | 2023-2024 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00020881
Prince Rupert Marine Station, Sourdough Bay - Current and Historical Operations in the vicinity |
Initial testing completed. No further action required. | 2008-2009 | 03 Initial Testing Program | |
00021003
Mathers Creek - Enhancement |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00021014
Naden Harbour Guardian Cabin |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00021044
Pallant Creek Hatchery |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00021106
Lower Stikine River Cabin |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00021227
Hartley Bay CEDP Hatchery |
Initial testing completed. Detailed testing underway. | 2023-2024 | 1 High Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00021230
Klemtu (Kitasoo) CEDP Hatchery |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00021413
Queen Charlotte City (Fill Material) |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00025864
676 - Haisla Nation - 07620 - KITAMAAT 2 - BC04851314 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00025972
676 - Haisla Nation - 07620 - KITAMAAT 2 - BC04871716 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00026557
673 - Metlakatla First Nation - 07754 - S1/2 TSIMPSEAN 2 - BC04887018 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00028047
Yakoun River near Port Clements |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00028108
Premier Creek near Daajing Giids |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 1 High Priority for Action | 06 Classify the site using the CCME National Classification System |
05023001
672 - Gitxaala Nation - 07734 - DOLPHIN ISLAND NO. 1 - 7000038194 |
Confirmatory sampling completed. No further action required. | 2009-2010 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05023002
672 - Gitxaala Nation - 07734 - DOLPHIN ISLAND 1 - 7000037994 |
Historical review completed. Initial testing underway. | 2023-2024 | 02 Historical Review | |
05037002
534 - Hagwilget Village Council - 06786 - HAGWILGET 1 - 7000108598 |
Historical review completed. Initial testing underway. | 2023-2024 | 02 Historical Review | |
05045003
671 - Nisga'a Village of Gingolx - 07705 - KINCOLITH 14 - 7000110398 |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05045004
671 - Nisga'a Village of Gingolx - 07705 - KINCOLITH NO. 14 - 7000110498 |
Confirmatory sampling completed. No further action required. | 2006-2007 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05045007
671 - Nisga'a Village of Gingolx - 07705 - KINCOLITH 14 - 7000110798 |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05045008
671 - Nisga'a Village of Gingolx - 07705 - KINCOLITH 14 - 7000110998 |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05046003
532 - Kispiox - 06761 - KISPIOX NO. 1 - 7000106298 |
Confirmatory sampling completed. No further action required. | 2008-2009 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05046004
532 - Kispiox - 06761 - KISPIOX NO. 1 - 7000123698 |
Confirmatory sampling completed. No further action required. | 2008-2009 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05046005
532 - Kispiox - 06761 - KISPIOX 1 - 7000106098 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05046006
532 - Kispiox - 06761 - KISPIOX NO. 1 - 7000106398 |
Confirmatory sampling completed. No further action required. | 2008-2009 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05046007
532 - Kispiox - 06761 - KISPIOX NO. 1 - 7000106498 |
Confirmatory sampling completed. No further action required. | 2008-2009 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05046008
532 - Kispiox - 06761 - KISPIOX 1 - 7000106598 |
Detailed testing completed. Remediation / risk management planned. | 2023-2024 | 2 Medium Priority for Action | 05 Detailed Testing Program |
05046009
532 - Kispiox - 06761 - KISPIOX 1 - 7000106698 |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
05046010
532 - Kispiox - 06761 - KISPIOX NO. 1 - 7000106798 |
Confirmatory sampling completed. No further action required. | 2008-2009 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05046012
532 - Kispiox - 06761 - KISPIOX NO. 1 - 7000105998 |
Confirmatory sampling completed. No further action required. | 2008-2009 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05046013
532 - Kispiox - 06761 - KISPIOX 1 - 7000106198 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05047001
540 - Kitasoo - 07886 - KITASOO NO. 1 - 7000040594 |
Long term monitoring completed. No further action required. | 2008-2009 | 1 High Priority for Action | 10 Long-Term Monitoring (Optional) |
05047002
540 - Kitasoo - 07886 - KITASOO NO. 1 - 7000040694 |
Confirmatory sampling completed. No further action required. | 2008-2009 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05047009
540 - Kitasoo - 07886 - KITASOO NO. 1 - 0902032405 |
Confirmatory sampling completed. No further action required. | 2008-2009 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05048002
681 - Kitsumkalum - 07646 - KITSUMKAYLUM 1 - 7000105398 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05053003
677 - Nisga'a Village of New Aiyansh - 07579 - NEW AIYANSH NO. 1 - 7000089697 |
Confirmatory sampling completed. No further action required. | 2008-2009 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05053005
674 - Lax Kw'alaams - 07770 - LAX KW'ALAAMS 1 - 7000111198 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05053009
674 - Lax Kw'alaams - 07770 - LAX KW'ALAAMS 1 - 7000017494 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05053010
674 - Lax Kw'alaams - 07770 - LAX KW'ALAAMS 1 - 7000017394 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 1 High Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
05083001
673 - Metlakatla - 07754 - S1/2 TSIMPSEAN 2 / 7000055495 |
Detailed testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05336001
677 - Nisga'a Village of New Aiyansh - 07579 - NEW AIYANSH 1 - 7000022094 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05336002
677 - Nisga'a Village of New Aiyansh - 07579 - NEW AIYANSH NO. 1 - 7000021994 |
Confirmatory sampling completed. No further action required. | 2010-2011 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05336003
677 - Nisga'a Village of New Aiyansh - 07579 - NEW AIYANSH 1 - 7000029594 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05336007
677 - Nisga'a Village of New Aiyansh - 07579 - NEW AIYANSH 1 - 7000097397 |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05336008
677 - Nisga'a Village of New Aiyansh - 07579 - NEW AIYANSH 1 - 7000097497 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05336010
677 - Nisga'a Village of New Aiyansh - 07579 - NEW AIYANSH 1 - 0902036505 |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
05337005
679 - Nisga'a Village of Gitwinksihlkw - 07614 - ZAULZAP NO. 29 - 7000108298 |
Confirmatory sampling completed. No further action required. | 2008-2009 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05337006
679 - Nisga'a Village of Gitwinksihlkw - 07613 - GITWINKSIHLKW NO. 7 - 7000108398 |
Confirmatory sampling completed. No further action required. | 2009-2010 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05337007
679 - Nisga'a Village of Gitwinksihlkw - 07613 - GITWINKSIHLKW 7 - 7000108498 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05362001
536 - Gitwangak - 06775 - GITWANGAK 1 - 7000067896 |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
05362006
536 - Gitwangak - 06775 - GITWANGAK 1 - 7000071396 |
Historical review completed. Initial testing underway. | 2023-2024 | 02 Historical Review | |
05362012
536 - Gitwangak - 06775 - GITWANGAK 1 - 7000107398 |
Historical review completed. Initial testing underway. | 2023-2024 | 02 Historical Review | |
05362013
536 - Gitwangak - 06775 - GITWANGAK 1 / 7000107498 |
Historical review completed. No further action required. | 2023-2024 | 02 Historical Review | |
05362014
536 - Gitwangak - 06775 - GITWANGAK 1 - 7000107598 |
Historical review completed. Initial testing underway. | 2023-2024 | 02 Historical Review | |
05362015
536 - Gitwangak - 06775 - GITWANGAK 1 / 7000108098 |
Historical review completed. Initial testing underway. | 2023-2024 | 02 Historical Review | |
05364001
683 - Iskut - 08363 - ISKUT 6 - 7000046494 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05364002
683 - Iskut - 08363 - ISKUT 6 - 7000046394 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05364005
683 - Iskut - 08363 - ISKUT 6 - 7000107098 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
05378001
677 - Nisga'a Village of New Aiyansh - 07580 - AIYANSH (KITLADAMAS) NO. 1 - 7000101398 |
Confirmatory sampling completed. No further action required. | 2010-2011 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05382008
530 - Witset First Nation - 06748 - MORICETOWN 1 - 7000103298 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
05382009
535 - Gitsegukla - 06772 - GITSEGUKLA 1 - 7000100798 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
19118080
675 - Gitga'at First Nation - 07846 - KULKAYU (HARTLEY BAY) 4 - BC04844613 |
Historical review completed. Initial testing underway. | 2023-2024 | 02 Historical Review | |
19118087
675 - Gitga'at First Nation - 07846 - KULKAYU (HARTLEY BAY) 4 - BC04844113 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
19118090
675 - Gitga'at First Nation - 07846 - KULKAYU (HARTLEY BAY) 4 - BC04845213 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
19341001
MA-1 Masset Rifle Range |
Remediation / risk management completed. No further action required. | 2020-2021 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
19401001
Langara Island |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
19482001
Bonilla Island - Sector Light |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
36286001
Rupert Inlet - Van Inlet |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
84357001
Lawn Point |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
84377001
Lucy Islands - Hydrocarbon Contamination Near the |
Remediation / risk management completed. No further action required. | 2021-2022 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |