FCSI Identifier Site Name |
Status | Fiscal Year | Classification | Highest Step Completed |
---|---|---|---|---|
00008376
Multipurpose runway Montreal Garrison north side |
Confirmatory sampling completed. No further action required. | 2012-2013 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00008378
Installation of an APU at building L-193 |
Detailed testing completed. No further action required. | 2013-2014 | I Insufficient Information | 07 Develop Remediation/Risk Management Strategy |
00008379
Layout of a salt shelter |
Remediation / risk management completed. No further action required. | 2012-2013 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00008398
Underground infrastructure replacement - Montréal Garrison |
Initial testing completed. No further action required. | 2016-2017 | 03 Initial Testing Program | |
00008428
Access ramp and docks repairs Montréal Garrison |
Initial testing completed. No further action required. | 2009-2010 | 03 Initial Testing Program | |
00008466
200 places prkng Mtl Garrison |
Remediation / risk management completed. No further action required. | 2013-2014 | N Not a Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00008694
Montreal soccer pitch |
Remediation / risk management completed. No further action required. | 2017-2018 | N Not a Priority for Action | 08 Implement Remediation/Risk Management Strategy |
07070002
Former Building 12 |
Confirmatory sampling completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
07070005
Enlargement of LAV III testing ramp at 202 WKP |
Confirmatory sampling completed. No further action required. | 2013-2014 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
07221005
L-10 South, ASU LP |
Remediation / risk management completed. No further action required. | 2013-2014 | N Not a Priority for Action | 08 Implement Remediation/Risk Management Strategy |
07221008
Used snow sites, ASU LP |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
07221020
Central thermal retaining wall, Bldg 37 Montreal Garrison |
Confirmatory sampling completed. No further action required. | 2014-2015 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |