00024670
Historic Military Base West of Runways - APEC 20C |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00028015
Area between Terminal Building and Control Tower - Former Biosystem Site |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
20146001
Air Terminal Building APEC 20A Parking Lot |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
20146003
Former Tenant Air Fuelling Facility - APEC 6 |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
20146004
Regional Fire Depot - APEC 8 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
20146005
Historical Hangars A, B, and C and Aprons APEC 10 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
20146009
Historical On-Site Buildings - APEC 40 |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
20146019
Operating Field Electrical Centre - APEC 17 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
20146023
Operating Maintenance Garage/Carpenter's Shop - APEC 9 |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
20146025
APEC 14B - Tennant Large AST Compound |
Initial testing completed. Detailed testing underway. | 2023-2024 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |