Results by Site Impact
Change results view to: Name and Location Contaminants and Media
FCSI Identifier Site Name |
Status | Fiscal Year | Classification | Highest Step Completed |
---|---|---|---|---|
N0281008
Former USTs (Maintenance Garage and Hangar) - APEC 6 |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0281002
Fire Training Area - APEC 1 |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0033001
Williams Lake Airport Former Fire Training Areas |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0017001
Fire Training Area |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0014002
Fire Training Area |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0013001
Fire Training Area |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0011003
Fire Training Area |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0010002
Fire Training Area |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0009001
Sault Ste. Marie Airport - Former Firefighting Training Area |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
N0002001
Old Fire Training Area |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
13252002
'Q' Area Fuel Storage Tanks |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
13201002
Fire Training Area |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
11943006
Former Neebing Landfill Site |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
11943001
Thunder Bay International Airport - Former Firefighting Training Area |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
10855008
Former Landfill - London Airport |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
10855002
London Airport - Former Firefighting Training Areas |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
06700001
Port Colborne - Marine Emergency Duties Training Centre |
Detailed testing completed. Remediation / risk management planned. | 2023-2024 | N Not a Priority for Action | 05 Detailed Testing Program |
04086002
Fire Training Area |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
03875003
Fire Training Area |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
01831002
North Side Property - All Areas |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00967005
Waste Material and Barrel Site |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00967003
Fire Training Area |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00339002
Disposal Site 2 and Fire Training Area |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00028031
Former firefighter training area (PFAS) |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00027732
Former Fire Training Area (PFAS) (Post 1976) |
Initial testing completed. Detailed testing underway. | 2023-2024 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00027681
Saskatoon Airport - Former Fire Training Area (FFTA) - South |
Initial testing completed. Detailed testing underway. | 2023-2024 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00027680
Saskatoon Airport - Former Fire Training Area (FFTA) - North |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00026126
Port Hardy Airport FTA (PFAS) |
Detailed testing completed. Remediation / risk management planned. | 2023-2024 | 2 Medium Priority for Action | 05 Detailed Testing Program |
00026125
Victoria Airport PFAS Stockpile |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 1 High Priority for Action | 06 Classify the site using the CCME National Classification System |
00026122
Prince George FTAs x4 (PFAS) |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 1 High Priority for Action | 06 Classify the site using the CCME National Classification System |
00026120
Former Fire Training Area (PFAS) (Pre-1976) |
Initial testing completed. Detailed testing underway. | 2023-2024 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00026119
Former Fire Training Area (PFAS) |
Detailed testing completed. Remediation / risk management planned. | 2023-2024 | 2 Medium Priority for Action | 05 Detailed Testing Program |
00026118
St. Anthony Airport Former Fire Training Area |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
00026117
Moncton Airport Former Fire Training Area |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00026116
Moncton Airport Fire Training Area |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00026115
Charlottetown Airport Former Fire Training Area |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00026114
Charlottetown Airport Fire Training Area |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00026113
Penticton Airport Former Fire Training Area (PFAS) |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00026112
Kuujjuaq - Former fire training area (PFAS) |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00026110
Former fire training area (PFAS) |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00026104
Former fire training area (PFAS) |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00026103
Former fire training area (PFAS) |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00026102
former fire training area (PFAS) |
Initial testing completed. Detailed testing underway. | 2023-2024 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00026101
Halifax Airport Former Fire Training Area |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00026099
Former Fire Training Area (PFAS) |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00026096
Sandspit Airport Former Fire Training Area (PFAS) |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 1 High Priority for Action | 06 Classify the site using the CCME National Classification System |