Search Results
Search Results Summary | |
---|---|
Criteria: |
|
Sort Key: | FCSI Identifier (ascending) |
Sites Found: | 124 |
Results by Site Impact
Change results view to: Name and Location Contaminants and Media
FCSI Identifier Site Name |
Status | Fiscal Year | Classification | Highest Step Completed |
---|---|---|---|---|
56488007
Former Barrel Storage |
Confirmatory sampling completed. No further action required. | 2013-2014 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
56488006
Former Fuel Storage Site (UST) |
Confirmatory sampling completed. No further action required. | 2013-2014 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
56488004
Waste Disposal Midden (East and West) |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
56488003
Prince of Wales Hotel |
Confirmatory sampling completed. No further action required. | 2013-2014 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
56488002
Trade Waste Pit |
Confirmatory sampling completed. No further action required. | 2013-2014 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
56488001
Park Works Compound |
Confirmatory sampling completed. No further action required. | 2013-2014 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
15841002
Garden River Old Dump |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
15841001
Hay Camp |
Remediation / risk management completed. No further action required. | 2021-2022 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
15457013
Abatoir Landfill |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
15457012
Gas/Diesel Filling Station |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15457011
Golf Course |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15457009
Garage outflow pipe |
Detailed testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
15457008
Recreational Landfill |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15457006
Administration Area Sewage Lagoon |
Detailed testing completed. No further action required. | 2021-2022 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
15457005
Recreational Area Sewage Lagoon |
Detailed testing completed. No further action required. | 2021-2022 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
15457004
South Entrance Landfill |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15457003
North Camp Landfill |
Initial testing completed. No further action required. | 2013-2014 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15457002
Old Parks Canada Maintenance Compound/Trade Waste Landfill |
Confirmatory sampling completed. No further action required. | 2013-2014 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
15457001
Parkway Landfill |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15412080
Snow Dump |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
15412079
Stormwater Outfall |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
15412078
X9 Highway 93 Km 15 |
Historical review completed. No further action required. | 2013-2014 | 02 Historical Review | |
15412077
X8 Miette Rd. Km 15 |
Initial testing completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15412075
Kerkeslin Borrow Pit |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15412074
X10 Highway 16 West, Km 20.6 |
Historical review completed. No further action required. | 2013-2014 | 02 Historical Review | |
15412073
X7 Pocahontas Mine (pits) |
Historical review completed. No further action required. | 2013-2014 | 02 Historical Review | |
15412072
X6 Maligne Lake |
Historical review completed. No further action required. | 2013-2014 | 02 Historical Review | |
15412071
X5 Ranger Creek |
Historical review not required. | 2017-2018 | 01 Identify Suspect Sites | |
15412070
X4 Wapiti Winter Camp |
Initial testing completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15412069
X3 Highway 93 Beauty Creek Borrow Pit |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
15412068
X2 93A - small pit |
Initial testing completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15412067
X1 Beauvert Lake Dump Site |
Initial testing completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15412066
Sunwapta Borrow Pit |
Initial testing completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15412019
C4 Miette Sewage Plant Site (Old Maintenance Area) |
Initial testing completed. No further action required. | 2017-2018 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15412018
Jasper National Park, C3 Townsite Block S Site |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
15412017
C2 JNP Tangle Creek Compound |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
15412016
C1 JNP Maintenance Compound |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
15412015
B1 Trade Waste Pit |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
15412014
A15 Sleepy Hollow Work Camp Site |
Initial testing completed. No further action required. | 2013-2014 | I Insufficient Information | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15412013
A14 Woodlot Landfill |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
15412012
A13 Sleepy Hollow Road / Waste Disposal Site |
Confirmatory sampling completed. No further action required. | 2018-2019 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
15412011
A11 Km 14.1 Miette Hot Springs Road Storage |
Initial testing completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15412010
A10 Km 10.5 Miette Hot Springs Road Borrow Pit |
Historical review completed. No further action required. | 2013-2014 | 02 Historical Review | |
15412009
A9 Km 1.6/2.0 Miette Road - Old Pocahontas Dump |
Historical review completed. Initial testing underway. | 2023-2024 | 02 Historical Review | |
15412008
A8 Pocahontas/Hwy #16 Dump/Fiddle Area Dump |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15412007
A7 Pyramid Bench |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
15412006
A6 Km 39.1 Maligne Lake Road Borrow Pit |
Initial testing completed. No further action required. | 2013-2014 | I Insufficient Information | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15412005
A5 Km 35.0 Maligne Lake Road Borrow Pit |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15412004
A4 Maligne Lake Road Borrow Pit |
Historical review completed. No further action required. | 2013-2014 | 02 Historical Review | |
15412003
A3 Km 29.7 Maligne Lake Road |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15412002
A2 Maligne Lake Dump |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15412001
A1 Waste Transfer Station |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
15404072
Banff Springs Golf Course |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
15404071
Castle Mountain Patrol Yard |
Initial testing completed. No further action required. | 2013-2014 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404070
Fairholme Ranch |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404069
Red Earth Creek Sawmill |
Historical review completed. No further action required. | 2013-2014 | 02 Historical Review | |
15404067
Banff Golf Course Dump |
Initial testing completed. No further action required. | 2021-2022 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404065
Cougar Avenue Dump |
Confirmatory sampling completed. No further action required. | 2013-2014 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
15404062
Bankhead Railsiding |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
15404061
Mount Coleman Rest Area |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404060
Fairview Lagoon |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404058
Old Government Horse Corral |
Detailed testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
15404055
Old Lake Louise Compound |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404047
Bow Summit Repeater Tower |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404045
Bow River Backwater |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404044
Forty Mile Creek Landfill |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
15404040
Silverhorn |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404038
Parks Canada Operations Compound |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
15404037
Mosquito Creek |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404034
Lake Louise Overflow |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404032
Saskatchewan Crossing Warden Station |
Confirmatory sampling completed. No further action required. | 2013-2014 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
15404031
Lake Louise Compound |
Confirmatory sampling completed. No further action required. | 2013-2014 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
15404022
Bankhead |
Initial testing completed. Detailed testing underway. | 2023-2024 | 1 High Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404016
Old Lake Louise Lumber Mill |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404015
Golf Course Dump |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404014
Castle Junction Tradewaste Site |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404013
Cascade Landfill |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 1 High Priority for Action | 06 Classify the site using the CCME National Classification System |
15404012
Cascade Borrow Pit |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404011
Carrot Creek Landfillsite |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
15404010
Peyto Pit |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
15404008
Minnewanka Landfill |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
15404006
Snow Dump/Abandonned Landfill |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
15404005
Niblock Pit |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
15404004
Fairview Pit |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404002
Stephen Pit |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15404001
Rimrock Dump |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00028172
Jasper National Park, Snaring Warden Station and Associated Buidlings |
Suspected site | |||
00027660
Kenow Fire Impacted Areas |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | I Insufficient Information | 07 Develop Remediation/Risk Management Strategy |
00026481
Banff Airstrip Site |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00026456
Jasper National Park Fish Hatchery |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00025822
Jasper NP Abandoned Oil Tank |
Confirmatory sampling completed. No further action required. | 2015-2016 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00025566
Anthracite Mine Site |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00024664
Ya-Ha-Tinda Ranch |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00023483
Airport Fuel Tank |
Confirmatory sampling completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00023482
Brewster Chalet |
Confirmatory sampling completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00023481
Jasper National Park - Municipal Sewage Lagoon |
Initial testing completed. Detailed testing underway. | 2023-2024 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00023455
Northwest Astotin Lake |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00023449
Sweetgrass Station Abattoir |
Historical review completed. No further action required. | 2013-2014 | 02 Historical Review | |
00023448
Northern Transport Company Sawmill near Sawmill Island |
Historical review completed. No further action required. | 2013-2014 | 02 Historical Review | |
00023447
Swanson's Sawmill Camp # 3 Peace River |
Historical review completed. No further action required. | 2013-2014 | 02 Historical Review | |
00023446
Swanson Camp 6 Sawmill at Sweetgrass Landing |
Historical review completed. No further action required. | 2013-2014 | 02 Historical Review | |
00023445
Church Historic AST |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00022830
Former Septic Tile Field |
Initial testing completed. No further action required. | 2013-2014 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00022829
Garden River Sewage Lagoon |
Historical review completed. No further action required. | 2021-2022 | 02 Historical Review | |
00022828
Northlands School Historic AST |
Initial testing completed. No further action required. | 2013-2014 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00022827
Garden River Landfill |
Initial testing completed. No further action required. | 2021-2022 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00022202
Garden River Trading (Charlie Rose) AST |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00022201
Fifth Meridian Market AST |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00022200
Garden River Public Works Yard |
Initial testing completed. No further action required. | 2021-2022 | 1 High Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00022198
Stalag Salt Storage |
Confirmatory sampling completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00013376
Castle Junction Household Dump |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00012861
Public Library Site |
Confirmatory sampling completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00012860
Old Banff Industrial Block |
Confirmatory sampling completed. No further action required. | 2013-2014 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00012859
Minnewanka Power Plant |
Initial testing completed. No further action required. | 2013-2014 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00012858
Parks Canada Landfill |
Initial testing completed. Detailed testing underway. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00012857
Bankhead Power Station |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00012856
Anthracite Townsite |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00012831
Lake Louise CPR Power House |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00012830
Bath Creek Tie Camp |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00012829
Lake Louise Service Station |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00008326
Athabasca Falls Warden Station |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00008325
Maligne Lake Warden Station |
Confirmatory sampling completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00008324
Sunwapta Warden Station |
Confirmatory sampling completed. No further action required. | 2013-2014 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00002336
Pine Lake Dump Site Barrel Cache |
Remediation / risk management completed. No further action required. | 2013-2014 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
- Version:
- 40