Search Results

Search Results Summary
Criteria:
  • Contaminant/Media Pair: Other organics / Soil
  • Contaminant Type: PCBs (Polychlorinated Biphenyl) and PCDD/Fs (polychlorinated dibenzo-p-dioxin/dibenzofuran)
Select Additional Criteria...
Sort Key:FCSI Identifier (descending)
Sites Found:55
Alternate Views
Choose an alternate view: Map XML CSV Financials Report
Results View Options

Results by Site Impact

Change results view to: Name and Location Contaminants and Media

FCSI Identifier
Site Name
Status Fiscal Year Classification Highest Step Completed
N7093001
CF-18 Crash Site - A/C 188745 (Aug. 05)
Confirmatory sampling completed. No further action required. 2018-2019 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
N7081001
BAR-E SRR (Horton River) - Site Summit
Detailed testing completed. No further action required. 2017-2018 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
C1050001
PIN B - CLIFTON POINT
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C1045001
PIN-E Cape Peel
Long term monitoring completed. No further action required. 2015-2016 2 Medium Priority for Action 10 Long-Term Monitoring (Optional)
C1044001
PIN C - BERNARD HARBOUR
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
C1042001
CAM B - HAT ISLAND
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
C1041001
CAM A - STURT POINT
Confirmatory sampling completed. No further action required. 2015-2016 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C1040001
PIN D - Ross Point
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
C1021001
FOX D - KIVITOO
Confirmatory sampling completed. No further action required. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C1018001
FOX 1 - ROWLEY ISLAND
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
C1003001
CAM E - KEITH BAY
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C1001001
CAM C - MATHESON POINT
Confirmatory sampling completed. No further action required. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
18976001
Power Plant at Det Holberg
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
17966001
Seal Bay Transmitter Site
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
15684031
Landfill Site 7
Initial testing completed. No further action required. 2017-2018 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15531016
Building 206 and 208
Confirmatory sampling completed. No further action required. 2015-2016 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
06651003
Demolition site, CEF Farnham
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
05613001
Mount Apica - north slope
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
05042021
688 - Tk'emlúps te Secwépemc - 07173 - KAMLOOPS 1 - 7000070696
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
05020004
642 - Cowichan - 06799 - COWICHAN 1 - 7000019894
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
02739026
Former EME Vehicle Maintenance Garage and Sewer - Aldershot
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
02739012
Meadowview Landfill - Aldershot
Long term monitoring completed. No further action required. 2017-2018 N Not a Priority for Action 10 Long-Term Monitoring (Optional)
02717131
Hangar 9, Former Tank 33
Historical review completed. No further action required. 2002-2003   02 Historical Review
01822094
Lower Tank Farm (LTF 2000 Series)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
01822076
Main Base and Civil Aviation Area
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
01822018
Canadian Side & Northside
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
00723001
Port aux Basques Ferry Terminal
Detailed testing completed. No further action required. 2018-2019 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
00028068
Consul Irrigation Project
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00024918
Shearwater Aircraft Burn Area (Site 252)
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024057
Montreal Road Complex ON
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00024052
Belza Farmhouse
Confirmatory sampling completed. No further action required. 2013-2014 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00008682
PIN-2A
Initial testing completed. No further action required. 2017-2018 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008681
PIN-CB
Initial testing completed. No further action required. 2017-2018 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008680
PIN-DA
Initial testing completed. No further action required. 2017-2018 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008678
CAM-A3A
Initial testing completed. No further action required. 2017-2018 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008674
LAB-6
Initial testing completed. No further action required. 2017-2018 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008667
FOX-2, Longstaff Bluff
Initial testing completed. No further action required. 2017-2018 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008663
BAR-4, Nicholson Peninsula
Initial testing completed. No further action required. 2017-2018 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008662
BAR-3, Tuktoyaktuk
Detailed testing completed. No further action required. 2017-2018 3 Low Priority for Action 05 Detailed Testing Program
00008661
BAR-1, Komakuk Beach
Detailed testing completed. No further action required. 2017-2018 3 Low Priority for Action 05 Detailed Testing Program
00008659
COL-40 Colwood North Western Bank of Dunn's Nook
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00008650
COL-31 Colwood Bldg 65
Detailed testing completed. Remedial action plan under development. 2023-2024 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00008612
DY-28 Dockyard Signal Hill Bldg 506 - Fmr Oil & Paint Stores
Initial testing completed. No further action required. 2018-2019   03 Initial Testing Program
00008550
PIN-1BG Croker River
Initial testing completed. No further action required. 2017-2018   03 Initial Testing Program
00008494
CAM-1A
Detailed testing completed. No further action required. 2017-2018 N Not a Priority for Action 05 Detailed Testing Program
00008458
YA-6 Yarrows Consolidatn Area Y-Gate
Confirmatory sampling completed. No further action required. 2022-2023 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008436
YA-4 Yarrows Former Shipyard
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008433
YA-5 Yarrows B - Lot Parking and Roads
Confirmatory sampling completed. No further action required. 2022-2023 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008387
Denison Armoury
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00008372
LAB-1, Cape Kakkiviak, SRR Site
Initial testing completed. No further action required. 2017-2018 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008368
Groundwater-monitoring perimeter - DND RTA/Shannon limit
Initial testing completed. No further action required. 2017-2018   03 Initial Testing Program
00007857
630 - Mowachaht/Muchalaht - 07044 - AHAMINAQUUS 12 - 0904777710
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00000994
Pesticide Container Landfill and Asphalt Dump
Initial testing completed. No further action required. 2015-2016   03 Initial Testing Program
00000989
Golf Course - landfill
Initial testing completed. No further action required. 2015-2016 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00000949
CAM-4 SRR (Pelly Bay, Nunavut Territory)- Site Summit
Remediation / risk management completed. No further action required. 2017-2018 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy