Search Results

Search Results Summary
Criteria:
  • Contaminant/Media Pair: Metal, metalloid, and organometallic / Soil
  • Economic Region: Kingston--Pembroke
Select Additional Criteria...
Sort Key:FCSI Identifier (ascending)
Sites Found:104
Alternate Views
Choose an alternate view: Map XML CSV Financials Report
Results View Options

Results by Site Impact

Change results view to: Name and Location Contaminants and Media

FCSI Identifier
Site Name
Status Fiscal Year Classification Highest Step Completed
00000969
AA Buildings
Initial testing completed. No further action required. 2018-2019 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00000970
BB Buildings
Detailed testing completed. No further action required. 2014-2015 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00000971
C Buildings
Historical review completed. Initial testing underway. 2023-2024   02 Historical Review
00000972
D Buildings
Initial testing completed. No further action required. 2010-2011   03 Initial Testing Program
00000976
Y Buildings
Initial testing completed. No further action required. 2010-2011   03 Initial Testing Program
00000977
Z Buildings
Initial testing completed. No further action required. 2009-2010   03 Initial Testing Program
00000980
Central Heating Plant
Detailed testing completed. No further action required. 2016-2017 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00000983
Garrison Training Areas
Historical review not required. 2016-2017   01 Identify Suspect Sites
00000986
Dump Site Adjacent to Ottawa River (south-east of Heliport)
Initial testing completed. No further action required. 2009-2010   03 Initial Testing Program
00000987
Liquid Waste Dump
Initial testing completed. No further action required. 2015-2016 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00000988
Landfills:locations not confirmed(Sites 6,7,9)
Initial testing completed. No further action required. 2009-2010   03 Initial Testing Program
00000990
Abandoned construction landfill
Initial testing completed. No further action required. 2015-2016   03 Initial Testing Program
00000991
Dry Solid Waste Landfill
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
00000992
Old Dump Site
Initial testing completed. No further action required. 2015-2016   03 Initial Testing Program
00008347
Cadet Camp Landfill & Firing Range
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00008420
CFB Petawawa RTA - Old Grenade Range
Long term monitoring completed. No further action required. 2018-2019 1 High Priority for Action 10 Long-Term Monitoring (Optional)
00012810
KINGSTON-PORTSMOUTH HARBOUR (Northeast portion of
Detailed testing completed. No further action required. 2021-2022 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00012845
Trenton Parking Lot
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00013120
Point Pleasant - Soil Near Remains of Tower Structure
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00013160
KINGSTON-PORTSMOUTH HARBOUR (Northwest corner of p
Detailed testing completed. No further action required. 2021-2022 I Insufficient Information 06 Classify the site using the CCME National Classification System
00013722
Arnprior Island - Around the navigational aid stru
Initial testing completed. No further action required. 2021-2022 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013733
Bateau Channel, 2 minor shore light - No Contamination Identified
Initial testing completed. No further action required. 2015-2016   03 Initial Testing Program
00013736
Bear Point - Around the navigational aid structure
Initial testing completed. No further action required. 2021-2022 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013741
Bissett Bay Point - Around the navigational aid s
Initial testing completed. No further action required. 2021-2022 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013774
Cassidy Shoal Minor Shore Light - in the area of t
Initial testing completed. No further action required. 2021-2022 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013777
Cedar Island - Close to the navigational aid
Initial testing completed. No further action required. 2021-2022 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013803
Deerhorn Rock - around navigational aid structure
Initial testing completed. No further action required. 2021-2022 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013805
Deux Rivières (Close to the navigational aid struc
Initial testing completed. No further action required. 2021-2022 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013810
False Duck Island - Former waste disposal area
Detailed testing completed. No further action required. 2015-2016 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
00013908
Mackay Point - Around the navigational aid structu
Initial testing completed. No further action required. 2021-2022 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013913
Marsh Lake Point - Around the navigational aid str
Initial testing completed. No further action required. 2021-2022 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013919
McQuestin Point - Around the navigational aid structure and the battery debris
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013943
Petawawa (Around the navigational aid structure)
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013954
Pigeon Island - Soils in the central-eastern portion of the site
Detailed testing completed. No further action required. 2012-2013 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00013999
Powell Creek - Around the navigational aid struct
Initial testing completed. No further action required. 2021-2022 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00014017
Scotch Bonnet Island - Soils throughout site
Detailed testing completed. No further action required. 2012-2013 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00014042
Stonecliffe (Around the navigational aid structure
Initial testing completed. No further action required. 2021-2022 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00014076
Wolfe Island (Quebec Head) - Northeast portion of the site
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00015114
Kingston MCTS (Odessa) (Around communication tower
Detailed testing completed. No further action required. 2021-2022 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00016574
KINGSTON (CONFEDERATION BASIN)(No Contamination Identified)
Initial testing completed. No further action required. 2008-2009 N Not a Priority for Action 03 Initial Testing Program
00024629
451-F01 Pittsburgh - Farmland
Initial testing completed. No further action required. 2011-2012   03 Initial Testing Program
00024633
401-C01 Regional Headquarters Ontario - Parking Lot
Confirmatory sampling completed. No further action required. 2011-2012 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00024663
441-L01 Collins Bay - Former Landfill at Northwest Corner of Property
Remediation / risk management completed. No further action required. 2017-2018 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00024738
441-C09 Frontenac Institution - Manure Composting at Sewage Lagoon
Detailed testing completed. No further action required. 2011-2012 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00024743
441-C25 Frontenac Institution - Debris Landfill
Remediation / risk management completed. No further action required. 2016-2017 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00024745
451-C11 Joyceville - Debris, Waste and Rubble at PP64
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
00024810
Hangar 5 & 6
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00025016
8 Wing 10 Hangar
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00025146
Petawawa Main Impact Area (MIA)
Historical review completed. Initial testing underway. 2023-2024   02 Historical Review
00025147
Petawawa - Area 9
Historical review completed. Initial testing underway. 2023-2024   02 Historical Review
00026073
416-C03 Kingston Penitentiary - Western exterior areas, Portsmouth Harbour side
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00026074
416-C04 Kingston Penitentiary - Exterior areas southern side
Remediation / risk management completed. No further action required. 2016-2017 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00026095
Kingston Coal Dock
Initial testing completed. No further action required. 2019-2020 1 High Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00026432
431-C01 Isabel MacNeil House Historical Use of Lead Base Paint
Remediation / risk management completed. No further action required. 2016-2017 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00026491
164 - Mohawks of the Bay of Quinte - 06217 - TYENDINAGA MOHAWK TERRITORY - ON04878217
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
05188002
164 - Mohawks of the Bay of Quinte - 06217 - TYENDINAGA MOHAWK TERRITORY / 3000105397
Detailed testing completed. No further action required. 2012-2013 2 Medium Priority for Action 05 Detailed Testing Program
05188003
164 - Mohawks of the Bay of Quinte - 06217 - TYENDINAGA MOHAWK TERRITORY - 3000010394
Detailed testing completed. No further action required. 2015-2016 2 Medium Priority for Action 05 Detailed Testing Program
05188005
164 - Mohawks of the Bay of Quinte - 06217 - TYENDINAGA MOHAWK TERRITORY / 3000103197
Initial testing completed. No further action required. 2012-2013   03 Initial Testing Program
05188006
164 - Mohawks of the Bay of Quinte - 06217 - TYENDINAGA MOHAWK TERRITORY / 3000116700
Initial testing completed. No further action required. 2012-2013   03 Initial Testing Program
07118001
Knapp Point (CCG Property)
Confirmatory sampling completed. No further action required. 2018-2019 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
09406001
Soil remediation Site/Abandoned Landfill, Gore Training Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
09406003
25 Yard Range North
Remediation / risk management completed. No further action required. 1998-1999 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
09406004
25 Yard Range Central
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
09406005
Correctional Services Canada Small Arms Range
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
09406006
75 Yard Small Arms Classification Range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
09406008
Abandoned Landfill - McNaughton Barracks
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
09406012
Sand and Salt Storage bldg E32 McN
Initial testing completed. No further action required. 2003-2004   03 Initial Testing Program
09406013
Sand and Salt Storage Bldg C40 McN
Initial testing completed. No further action required. 2002-2003   03 Initial Testing Program
09406019
A12 McNaughton
Initial testing completed. No further action required. 2003-2004   03 Initial Testing Program
09407006
R26 Fort Henry Heights Dump site
Initial testing completed. No further action required. 2014-2015   03 Initial Testing Program
09407009
Fort Henry Heights R3, R4
Long term monitoring completed. No further action required. 2013-2014 3 Low Priority for Action 10 Long-Term Monitoring (Optional)
09451002
Parking lot (Old Post Office)
Remediation / risk management completed. No further action required. 2009-2010 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
09451003
Parking lot (Old Post Office)
Remediation / risk management completed. No further action required. 2009-2010 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
09451004
Parking lot (Old Post Office)
Remediation / risk management completed. No further action required. 2009-2010 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
09461001
Graving Dock
Remediation / risk management completed. No further action required. 2015-2016 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
09530001
Office Building (11 Station Street)
Remediation / risk management completed. No further action required. 2009-2010 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
09540002
Northwest Bldg 52
Long term monitoring completed. No further action required. 2013-2014 N Not a Priority for Action 10 Long-Term Monitoring (Optional)
09540005
EME Shop, Bldg 113 and Skeet Range
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
09540009
Middleton Park Landfill Site
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
09540010
AMDU Landfill Site
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
09540012
8 W Fire Fighting Training Area /Hazardous Materials Storage
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
09585001
Prince Edward Point - South and West of light
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
09609003
Smithfield Research Farm
Detailed testing completed. No further action required. 2011-2012 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
11318002
Area F (woodwaste disposal sites)
Confirmatory sampling completed. No further action required. 2015-2016 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
11318003
Area B (former maintenance building)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
11318004
Area C (leaching field of former septic tank C-1 & PHC impacts to the south of hangar)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
11318005
Area D (leaching field of former septic tank D-1)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
11318008
Area G (former lumber yard)
Remediation / risk management completed. No further action required. 2015-2016 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
11347007
Old Rifle Range / Biathlon Range
Confirmatory sampling completed. No further action required. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
22851001
Prince Edward Point NWA (Consolidated)
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
23290001
Des Allumettes Bridge (Ontario Side)
Remediation / risk management completed. No further action required. 2020-2021 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
30246001
BELLEVILLE (Zwick's East Landfill)
Detailed testing completed. No further action required. 2013-2014 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
34476001
Mountain View - Outer Landfill Site
Detailed testing completed. No further action required. 2017-2018 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
34476004
Mtn View - Inner Landfill Site
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
36439001
False Duck Island-Southern portion of the fenced compound and the vicinity of Former dwelling # 2 and Former dwelling # 1.
Detailed testing completed. No further action required. 2013-2014 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
56058001
Irvine Point - Front Range (LL 380)
Detailed testing completed. No further action required. 2014-2015 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
56058002
Irvine Point - Rear Range (LL 381)
Detailed testing completed. No further action required. 2014-2015 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
56060001
Main Duck Island - Inside & Outside CG Compound
Detailed testing completed. No further action required. 2013-2014 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
58204001
Nine Mile Point - W, N and E of light station
Confirmatory sampling completed. No further action required. 2012-2013 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
67606001
Brothers Islands - Soils, former lighthouse area
Detailed testing completed. No further action required. 2020-2021 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
83478001
Shermans Point - Around light station
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
83493001
Pig Point - Navigational Aid
Detailed testing completed. No further action required. 2020-2021 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
83865001
Deep River Islet L.L 1311 - Surrounding navigational aid
Detailed testing completed. No further action required. 2020-2021 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
85098001
Telegraph Island - Adjacent to Foundation of Tower
Detailed testing completed. No further action required. 2021-2022 3 Low Priority for Action 06 Classify the site using the CCME National Classification System