Search Results

Search Results Summary
Criteria:
  • Media Type: Groundwater
  • Economic Region: Toronto
Select Additional Criteria...
Sort Key:FCSI Identifier (ascending)
Sites Found:41
Alternate Views
Choose an alternate view: Map XML CSV Financials Report
Results View Options

Results by Site Impact

Change results view to: Name and Location Contaminants and Media

FCSI Identifier
Site Name
Status Fiscal Year Classification Highest Step Completed
00008360
HMCS York
Detailed testing completed. No further action required. 2022-2023 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00008381
Moss Park Armoury
Detailed testing completed. No further action required. 2017-2018 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00008382
Canadian Forces Staff College
Initial testing completed. No further action required. 2022-2023   03 Initial Testing Program
00008383
Mosley Street Armoury
Initial testing completed. No further action required. 2014-2015 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008384
Fort York //
Detailed testing completed. No further action required. 2017-2018 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00008385
Todd Road Armoury
Initial testing completed. No further action required. 2011-2012   03 Initial Testing Program
00008386
Oshawa Airport
Initial testing completed. No further action required. 2011-2012   03 Initial Testing Program
00008387
Denison Armoury
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00008572
Etobicoke Armoury
Historical review completed. No further action required. 2016-2017   02 Historical Review
00012660
KESWICK (JERSEY RIVER) ( South Breakwater)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00014055
Toronto Main Harbour Channel Front (Daybeacon)
Initial testing completed. No further action required. 2013-2014 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00022935
WHITBY (Promenade Park & Former Texaco Tank Farm (adjacent site))
Detailed testing completed. Remediation / risk management planned. 2023-2024 2 Medium Priority for Action 05 Detailed Testing Program
00022940
WHITBY (Historical Inlet (backfilled)/Confined Disposal Facility)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00022941
WHITBY (Port Whitby Marina and Shoreline Extension (backfilling))
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00024058
Airport Lands Adjacent to Skeet Club
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00024673
PIN 614461.1
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00025354
WHITBY (Public Boat Launch Area)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00025563
Pickering Lands Site PIN 614225
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00026081
PIN 614334.1-B
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
00026093
Pickering Lands Site PIN 614229
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
09820002
PIN 614053.2
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
09820008
PIN 614107 - Wooded Lot
Confirmatory sampling completed. No further action required. 2014-2015 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
09820013
PIN 614224
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
09820015
PIN 614272.2
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
09820028
Drinking water wells - aesthetic concerns
Remediation / risk management completed. No further action required. 2011-2012 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
09820029
Drinking water wells
Remediation / risk management completed. No further action required. 2014-2015 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
09820043
PIN 614645
Confirmatory sampling completed. No further action required. 2019-2020 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
09820050
PIN 614726
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
09820052
PIN 614699
Detailed testing completed. Remedial action plan under development. 2023-2024 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
09820053
PIN 614649/650
Detailed testing completed. Remedial action plan under development. 2023-2024 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
09820054
PIN 614698
Detailed testing completed. No further action required. 2019-2020 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
09820055
PIN 614380
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
09834001
310 Simcoe St.south, Oshawa
Initial testing completed. No further action required. 2011-2012 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
09976001
Arthur Meighen Building
Detailed testing completed. No further action required. 2017-2018 N Not a Priority for Action 05 Detailed Testing Program
54117001
Burlington Lift Bridge (Parcel A)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
67590004
Area D (Rail Spur)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
67590005
Area E (Marina)
Remediation / risk management completed. No further action required. 2016-2017 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
67590008
Area C - Marina/waterlot
Detailed testing completed. No further action required. 2011-2012 I Insufficient Information 07 Develop Remediation/Risk Management Strategy
70602002
Central Heating Plant (Downsview)
Confirmatory sampling completed. No further action required. 2012-2013 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
70602004
Auto Hobby Club Former DeHavilland Plant Area (Downsview)
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
70602015
Former POL Compound Building 107 (Downsview)
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program