Search Results
Search Results Summary | |
---|---|
Criteria: |
|
Sort Key: | FCSI Identifier (ascending) |
Sites Found: | 230 |
Results by Site Impact
Change results view to: Name and Location Contaminants and Media
FCSI Identifier Site Name |
Status | Fiscal Year | Classification | Highest Step Completed |
---|---|---|---|---|
00022905
Sediments around wharf |
Initial testing completed. No further action required. | 2013-2014 | 03 Initial Testing Program | |
00022906
Sediments around wharf |
Initial testing completed. No further action required. | 2011-2012 | 03 Initial Testing Program | |
00306001
Public Harbour and Wharf |
Detailed testing completed. No further action required. | 2014-2015 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00339011
Former Operations Area |
Detailed testing completed. No further action required. | 2011-2012 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00670001
Public Harbour and Wharf (Service Station) |
Historical review not required. | 2011-2012 | 01 Identify Suspect Sites | |
00670002
Helicopter Site |
Long term monitoring completed. No further action required. | 2011-2012 | 1 High Priority for Action | 10 Long-Term Monitoring (Optional) |
00967003
Fire Training Area |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00967015
Fuel Hydrant System and Former Gas Station Site |
Detailed testing completed. No further action required. | 2014-2015 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00967016
Former Gas Station Site |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00967021
Former Coal Storage Location |
Detailed testing completed. No further action required. | 2018-2019 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00967025
Former USAF POL Underground Storage |
Confirmatory sampling completed. No further action required. | 2013-2014 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00967029
Former Underground Storage Tank Site |
Confirmatory sampling completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00967031
Former Powerhouse |
Confirmatory sampling completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00967033
Waste Oil UST |
Confirmatory sampling completed. No further action required. | 2013-2014 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00967034
Former Fuel Storage USTs |
Confirmatory sampling completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00967035
Former UST Site |
Confirmatory sampling completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00967038
Former AST Site |
Confirmatory sampling completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00967040
Former Tank Farm |
Initial testing completed. No further action required. | 2013-2014 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00967042
Hanger 22 Fuel Hydrant System |
Detailed testing completed. No further action required. | 2014-2015 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00967043
Fuel Contaminated Site |
Confirmatory sampling completed. No further action required. | 2018-2019 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00967059
Former Remote Radar Site |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
01831001
Otter Creek Former Landfill / Asphalt Plant |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
01898001
Former JP4 Fuel USTs Issue TC-F-U2 and TC-F-U3 Contaminated Soil Stockpile |
Confirmatory sampling completed. No further action required. | 2021-2022 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
01898004
Former Fire Training Area Issue TC-L-S13 |
Detailed testing completed. No further action required. | 2011-2012 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
01898005
Fire Training Area Issue TC-P-S18 |
Detailed testing completed. No further action required. | 2011-2012 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
01955001
Sediment POD |
Detailed testing completed. No further action required. | 2011-2012 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
02131007
Former Coast Guard Hangar |
Initial testing completed. No further action required. | 2015-2016 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
02131010
Former FTA/Airconsol Tank Farm |
Initial testing completed. No further action required. | 2015-2016 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
03057001
Fire Training Area (FTA) |
Remediation / risk management completed. No further action required. | 2021-2022 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
03057005
Air Canada & Air Canada Cargo (Bennery Brook) |
Remediation / risk management completed. No further action required. | 2011-2012 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
03057011
Maintenance Area (Bennery Brook) |
Confirmatory sampling completed. No further action required. | 2019-2020 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
03057012
Field Electrical Centre (FEC) |
Detailed testing completed. No further action required. | 2011-2012 | I Insufficient Information | 06 Classify the site using the CCME National Classification System |
03057015
Old Service Station (OSS) |
Detailed testing completed. No further action required. | 2011-2012 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
03057016
Air Terminal Building (ATB) |
Initial testing completed. No further action required. | 2011-2012 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
03875003
Fire Training Area |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
04086002
Fire Training Area |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
04086003
Former Norfolk Hangar |
Initial testing completed. No further action required. | 2011-2012 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
04363001
Old Fire Training Area |
Remediation / risk management completed. No further action required. | 2021-2022 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
04363002
Maintenance Garage |
Initial testing completed. No further action required. | 2011-2012 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
04363003
Old Fuel Tank Farm Area and Present Shell and Airconsol Site |
Initial testing completed. No further action required. | 2011-2012 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
04363005
Dump Site (Area 5) |
Confirmatory sampling completed. No further action required. | 2011-2012 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05031004
Sediments around wharf |
Detailed testing completed. Remediation / risk management planned. | 2023-2024 | 2 Medium Priority for Action | 05 Detailed Testing Program |
05519001
Installation |
Detailed testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05521001
installation |
Detailed testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05570001
Sediments around wharf |
Confirmatory sampling completed. No further action required. | 2012-2013 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05582001
Harbour sediments |
Confirmatory sampling completed. No further action required. | 2012-2013 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
05871001
Former dump |
Long term monitoring completed. No further action required. | 2011-2012 | 3 Low Priority for Action | 10 Long-Term Monitoring (Optional) |
05871002
Former firefighter training site |
Long term monitoring completed. No further action required. | 2011-2012 | 3 Low Priority for Action | 10 Long-Term Monitoring (Optional) |
05871003
Entrance road |
Initial testing completed. No further action required. | 2011-2012 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
05871004
Stockpiled contaminated soil from entrance road |
Confirmatory sampling completed. No further action required. | 2011-2012 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
06715005
Former petroleum depot (Marcoux) |
Confirmatory sampling completed. No further action required. | 2011-2012 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
06985001
Former firefighter training site |
Detailed testing completed. No further action required. | 2011-2012 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
06985002
Depot C - occupied by lessee |
Remediation / risk management completed. No further action required. | 2011-2012 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
06985003
Vacant site (lot 12) -firefighter training site No. 2 |
Remediation / risk management completed. No further action required. | 2011-2012 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
06985004
Lot 9 - former petroleum depot |
Remediation / risk management completed. No further action required. | 2011-2012 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
06985006
Site H |
Remediation / risk management completed. No further action required. | 2011-2012 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
08040001
Site occupied by lessee |
Detailed testing completed. No further action required. | 2018-2019 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
08201001
Harbour sediments |
Remediation / risk management completed. No further action required. | 2012-2013 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
08309001
NDB site |
Long term monitoring completed. No further action required. | 2014-2015 | 2 Medium Priority for Action | 10 Long-Term Monitoring (Optional) |
08708003
Area T-99 (TC Aviation Services) |
Initial testing completed. No further action required. | 2016-2017 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
08708005
Bulk fuel storage facility (Esso Tank Farm) - Ottawa Macdonald-Cartier International Airport |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
08708006
East end of Building T-96 |
Detailed testing completed. No further action required. | 2015-2016 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
08708007
Building T107 (Shell Tank Farm) - Ottawa Macdonald-Cartier International Airport |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
08708008
East end of Building T-96 (National Car Rental facility) |
Confirmatory sampling completed. No further action required. | 2015-2016 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
08708011
DND's Petroleum, oils & lubricants (POL) Compound |
Initial testing completed. No further action required. | 2016-2017 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
09820001
PIN 614048 |
Detailed testing completed. No further action required. | 2014-2015 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09820002
PIN 614053.2 |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
09820004
PIN 614076 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09820005
PIN 614078 |
Confirmatory sampling completed. No further action required. | 2014-2015 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
09820006
PIN 614104.2 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09820007
PIN 614106 |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
09820009
PIN 614120 |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
09820010
PIN 614126 |
Confirmatory sampling completed. No further action required. | 2014-2015 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
09820011
PIN 614132 |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
09820016
PIN 614306 |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
09820017
PIN 614312 |
Confirmatory sampling completed. No further action required. | 2015-2016 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
09820019
PIN 614338.2 |
Confirmatory sampling completed. No further action required. | 2014-2015 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
09820020
PIN 614353 |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
09820022
PIN 614414.1 |
Confirmatory sampling completed. No further action required. | 2015-2016 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
09820024
PIN 614520 |
Confirmatory sampling completed. No further action required. | 2014-2015 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
09820026
PIN 614581 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09820030
PIN 614175 |
Confirmatory sampling completed. No further action required. | 2014-2015 | I Insufficient Information | 09 Confirmatory Sampling and Final Reporting |
09820031
PIN 614127 |
Confirmatory sampling completed. No further action required. | 2014-2015 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
09820032
PIN 614070.1 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09820033
PIN 614458 |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | N Not a Priority for Action | 08 Implement Remediation/Risk Management Strategy |
09820035
PIN 614142 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09820036
PIN 614048-A |
Detailed testing completed. No further action required. | 2014-2015 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09820037
PIN 614048-B |
Detailed testing completed. No further action required. | 2014-2015 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09820039
PIN 614635 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09820040
PIN 614547 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
10179001
Fuel island |
Remediation / risk management completed. No further action required. | 2011-2012 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
10179002
CAFOT - Finger 6 |
Detailed testing completed. No further action required. | 2011-2012 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
10352002
Site #2 Vacant lands between Rodney St. to East Breakwater in Port Colborne. Bottom half of property near Inco plant. Dir |
Remediation / risk management completed. No further action required. | 2010-2011 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
10611003
Harbour Bottom |
Detailed testing completed. No further action required. | 2013-2014 | 1 High Priority for Action | 06 Classify the site using the CCME National Classification System |
10855006
Metal-clad building - London Airport |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
11867001
SSM Harbour Bed |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
11943002
Thunder Bay Hangar (NOASARA) |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
11943003
Waste oil tank - (Former Confederation College, Paipoonge Hangar) |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
11943004
Waste oil tank #2 (Bearskin Airlines) |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
11943007
Underground storage tanks (Former AVIS) |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
11943008
Waste Oil Tank #3 (Thunder Bay Flying School) |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | N Not a Priority for Action | 08 Implement Remediation/Risk Management Strategy |
12738001
Fire Training Area |
Detailed testing completed. No further action required. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
12738002
Building T-38 |
Initial testing completed. No further action required. | 2010-2011 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
12738003
Building T-120 |
Initial testing completed. No further action required. | 2021-2022 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
14131001
Central Heating Plant |
Initial testing completed. No further action required. | 2011-2012 | I Insufficient Information | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
14131002
Purolator Courier Ltd. Leased Site |
Detailed testing completed. No further action required. | 2011-2012 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
14131004
Fire Training Area |
Long term monitoring completed. No further action required. | 2013-2014 | I Insufficient Information | 10 Long-Term Monitoring (Optional) |
14901001
Uplands |
Confirmatory sampling completed. No further action required. | 2011-2012 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
15157001
Leased Site |
Confirmatory sampling completed. No further action required. | 2010-2011 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
15473001
Fire Training Area |
Long term monitoring completed. No further action required. | 2012-2013 | 2 Medium Priority for Action | 10 Long-Term Monitoring (Optional) |
15473002
Field Maintenance Building |
Initial testing completed. No further action required. | 2010-2011 | I Insufficient Information | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15473003
Former Tank Farm Area |
Initial testing completed. No further action required. | 2012-2013 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15473004
Old Landfill |
Initial testing completed. No further action required. | 2010-2011 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
15751001
Air Navigation Facility: Non Directional Beacon |
Confirmatory sampling completed. No further action required. | 2011-2012 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
16781004
Former Car Rental Area |
Confirmatory sampling completed. No further action required. | 2011-2012 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
16781007
N5 Apron Area |
Initial testing completed. No further action required. | 2011-2012 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
17139002
Dumpsite I (East Dump Site) |
Confirmatory sampling completed. No further action required. | 2018-2019 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
17139003
Dumpsite II (West Dumpsite) |
Confirmatory sampling completed. No further action required. | 2018-2019 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
17348003
Lot 2A: Middle Harbour Fill Site; Harbour Floor |
Detailed testing completed. No further action required. | 2021-2022 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
18082002
Uplands (suspected fuel line area) |
Confirmatory sampling completed. No further action required. | 2016-2017 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
19793003
Site 7 - Former Fire Training Area |
Remediation / risk management completed. No further action required. | 2015-2016 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
19793004
Site 21 & 28 - Apron refuelling area & former UST location |
Remediation / risk management completed. No further action required. | 2015-2016 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
19793009
Site 20 - Former UST Site |
Remediation / risk management completed. No further action required. | 2015-2016 | N Not a Priority for Action | 08 Implement Remediation/Risk Management Strategy |
19793010
Site 9 - Former Fire Training Area |
Confirmatory sampling completed. No further action required. | 2017-2018 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
19793018
Site 39 - Former UST nest |
Remediation / risk management completed. No further action required. | 2016-2017 | N Not a Priority for Action | 08 Implement Remediation/Risk Management Strategy |
20146002
Yukon Transportation Museum |
Detailed testing completed. No further action required. | 2019-2020 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
20146003
Former Tenant Air Fuelling Facility - APEC 6 |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
20146004
Regional Fire Depot - APEC 8 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
20146005
Historical Hangars A, B, and C and Aprons APEC 10 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
20146007
Historic On-Site Fuel Distribution Pipeline - APEC 14A |
Initial testing completed. No further action required. | 2012-2013 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
20146010
Former Fire Hall (Current Sand Storage Building) - APEC 4 |
Initial testing completed. No further action required. | 2019-2020 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
20146012
Historic 6 Bay Garage - APEC 11 |
Remediation / risk management completed. No further action required. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
20146013
Historic Fleet Fuelling Station - APEC 5 |
Confirmatory sampling completed. No further action required. | 2015-2016 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
20146016
Historic Upper Air Weather Station - APEC 21 |
Initial testing completed. No further action required. | 2020-2021 | 03 Initial Testing Program | |
20146018
Former Drums in Baxter's Ravine - APEC 1 |
Initial testing completed. No further action required. | 2011-2012 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
20146020
Off-Site Fuel Distribution System - APEC 48 |
Historical review completed. No further action required. | 2011-2012 | 02 Historical Review | |
20146021
Operating Fire Hall/Tenant Cargo Facility - APEC 13 |
Initial testing completed. No further action required. | 2011-2012 | 03 Initial Testing Program | |
20146024
Tenant Tanker Base - APEC 28 |
Detailed testing completed. No further action required. | 2022-2023 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
21956003
Owen Sound Harbour - Land Lots |
Confirmatory sampling completed. No further action required. | 2018-2019 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
22905003
PIN 10 |
Confirmatory sampling completed. No further action required. | 2011-2012 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
22905006
PIN 24 |
Remediation / risk management completed. No further action required. | 2014-2015 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
56040001
Ops Area |
Confirmatory sampling completed. No further action required. | 2011-2012 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
56053001
Lobster Rock Wharf |
Long term monitoring completed. No further action required. | 2002-2003 | I Insufficient Information | 10 Long-Term Monitoring (Optional) |
72078001
Area 1 |
Remediation / risk management completed. No further action required. | 2011-2012 | I Insufficient Information | 08 Implement Remediation/Risk Management Strategy |
72078002
Area 2 |
Initial testing completed. No further action required. | 2011-2012 | 03 Initial Testing Program | |
72078003
Area 3 |
Initial testing completed. No further action required. | 2011-2012 | 03 Initial Testing Program | |
72078004
Area 4 |
Initial testing completed. No further action required. | 2011-2012 | 03 Initial Testing Program | |
N0001002
Fire Training Area |
Confirmatory sampling completed. No further action required. | 2011-2012 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N0002001
Old Fire Training Area |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0002002
Solid Waste Dump |
Detailed testing completed. No further action required. | 2014-2015 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0002003
Southern Fuel Distribution Lines |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0002004
East Apron Hydrants |
Detailed testing completed. No further action required. | 2011-2012 | I Insufficient Information | 05 Detailed Testing Program |
N0002005
Eastern Fuel Distribution Lines |
Detailed testing completed. No further action required. | 2019-2020 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0002006
Valve Chamber 16 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0002007
Field Electrical Centre |
Detailed testing completed. No further action required. | 2019-2020 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0002008
CSB Area A |
Detailed testing completed. No further action required. | 2020-2021 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0002009
CSB Area B |
Detailed testing completed. No further action required. | 2011-2012 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0002010
Building T-257 |
Detailed testing completed. No further action required. | 2019-2020 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0002011
West Apron Hydrants |
Detailed testing completed. No further action required. | 2015-2016 | I Insufficient Information | 07 Develop Remediation/Risk Management Strategy |
N0002012
Abandoned Refuelling Foundation |
Detailed testing completed. No further action required. | 2020-2021 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0002013
Building T5 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0002014
Building T6 |
Detailed testing completed. No further action required. | 2014-2015 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0002015
Building T8 |
Detailed testing completed. No further action required. | 2021-2022 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0002016
West side of west apron |
Initial testing completed. No further action required. | 2011-2012 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
N0002017
Runway Approach (Muddy Pond) |
Initial testing completed. No further action required. | 2011-2012 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
N0002018
Barrel Dump Area |
Confirmatory sampling completed. No further action required. | 2014-2015 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N0002019
Active West Apron |
Confirmatory sampling completed. No further action required. | 2020-2021 | I Insufficient Information | 09 Confirmatory Sampling and Final Reporting |
N0005001
Fire Training Area |
Long term monitoring completed. No further action required. | 2010-2011 | I Insufficient Information | 10 Long-Term Monitoring (Optional) |
N0007001
Offsite Plume (Area 9) |
Long term monitoring completed. No further action required. | 2014-2015 | 2 Medium Priority for Action | 10 Long-Term Monitoring (Optional) |
N0007002
On-site Plume (Areas 2, 8 and 10) |
Long term monitoring completed. No further action required. | 2014-2015 | 2 Medium Priority for Action | 10 Long-Term Monitoring (Optional) |
N0010001
Screening Plant/Boneyard |
Confirmatory sampling completed. No further action required. | 2012-2013 | I Insufficient Information | 09 Confirmatory Sampling and Final Reporting |
N0010003
Former Tank Farm |
Detailed testing completed. No further action required. | 2012-2013 | I Insufficient Information | 07 Develop Remediation/Risk Management Strategy |
N0010004
Former AST Location North of T-5. |
Confirmatory sampling completed. No further action required. | 2012-2013 | I Insufficient Information | 09 Confirmatory Sampling and Final Reporting |
N0011001
Old Maintenance Garage UST and AST |
Remediation / risk management completed. No further action required. | 2023-2024 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0011003
Fire Training Area |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0011004
Field Electrical Centre |
Confirmatory sampling completed. No further action required. | 2011-2012 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N0013001
Fire Training Area |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0014001
Maintenance Garage |
Long term monitoring completed. No further action required. | 2012-2013 | I Insufficient Information | 10 Long-Term Monitoring (Optional) |
N0014002
Fire Training Area |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0015001
Former USAF Tank Farm |
Confirmatory sampling completed. No further action required. | 2014-2015 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N0015002
Fire Training Area |
Confirmatory sampling completed. No further action required. | 2017-2018 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N0015005
Bitumen Drum Cache - Iqaluit Airport |
Confirmatory sampling completed. No further action required. | 2012-2013 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N0016001
Air Services Building |
Confirmatory sampling completed. No further action required. | 2010-2011 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N0016002
Fire Training Area |
Remediation / risk management completed. No further action required. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0016003
Old Land Treatment Unit (LTU) |
Confirmatory sampling completed. No further action required. | 2012-2013 | I Insufficient Information | 09 Confirmatory Sampling and Final Reporting |
N0017001
Fire Training Area |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0017002
Building #4 |
Confirmatory sampling completed. No further action required. | 2012-2013 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N0018001
Bulk Storage Tanks |
Initial testing completed. No further action required. | 2019-2020 | 1 High Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
N0018004
Leased Site |
Long term monitoring completed. No further action required. | 2012-2013 | 2 Medium Priority for Action | 10 Long-Term Monitoring (Optional) |
N0018005
Snow Dump Area/Landfill |
Initial testing completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
N0020001
Former Fire Training Area |
Confirmatory sampling completed. No further action required. | 2013-2014 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N0028001
Former Fire Training Area |
Confirmatory sampling completed. No further action required. | 2011-2012 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N0030001
Former Fire Training Area |
Confirmatory sampling completed. No further action required. | 2011-2012 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N0030005
Site C - Old Maintenance Garage UST nest |
Confirmatory sampling completed. No further action required. | 2011-2012 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N0032005
Former Powerhouse |
Confirmatory sampling completed. No further action required. | 2013-2014 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N0032006
Creek A |
Confirmatory sampling completed. No further action required. | 2013-2014 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N0033002
Former UST/Dispenser Area |
Detailed testing completed. No further action required. | 2016-2017 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0037002
Tenant Underground Storage Tanks |
Initial testing completed. No further action required. | 2010-2011 | 03 Initial Testing Program | |
N0037003
Two Former Underground Storage Tanks |
Initial testing completed. No further action required. | 2010-2011 | 03 Initial Testing Program | |
N0037008
Puddled Asphalt |
Initial testing completed. No further action required. | 2010-2011 | 03 Initial Testing Program | |
N0037009
Industrial Building formerly occupied by a sheet metal fabrication company |
Historical review completed. No further action required. | 2010-2011 | 02 Historical Review | |
N0074002
Uplands |
Detailed testing completed. No further action required. | 2010-2011 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
N0090001
Iron Rack |
Remediation / risk management completed. No further action required. | 2015-2016 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0090002
Zone 1 & 2 Area North of Graving Dock |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0090003
Zone 3 - Area West of Graving Dock |
Detailed testing completed. No further action required. | 2015-2016 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0137001
Fire Training Area |
Long term monitoring completed. No further action required. | 2013-2014 | 1 High Priority for Action | 10 Long-Term Monitoring (Optional) |
N0137002
Former Underground Fuel Storage Tank Site |
Long term monitoring completed. No further action required. | 2013-2014 | I Insufficient Information | 10 Long-Term Monitoring (Optional) |
N0138001
Fire Training Area |
Confirmatory sampling completed. No further action required. | 2010-2011 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N0201001
Former (CN) Valley Car Shop Property |
Remediation / risk management completed. No further action required. | 2011-2012 | I Insufficient Information | 08 Implement Remediation/Risk Management Strategy |
N0202001
Former CN Yard, Corner Brook |
Detailed testing completed. No further action required. | 2012-2013 | I Insufficient Information | 05 Detailed Testing Program |
N0203001
Area 5 |
Long term monitoring completed. No further action required. | 2011-2012 | I Insufficient Information | 10 Long-Term Monitoring (Optional) |
N0203002
Area 6 |
Long term monitoring completed. No further action required. | 2011-2012 | I Insufficient Information | 10 Long-Term Monitoring (Optional) |
N0203003
Area 7 |
Long term monitoring completed. No further action required. | 2011-2012 | I Insufficient Information | 10 Long-Term Monitoring (Optional) |
N0240001
Port of Churchill Wharf |
Remediation / risk management completed. No further action required. | 2014-2015 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0281002
Fire Training Area - APEC 1 |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0281004
Terminal Area |
Initial testing completed. No further action required. | 2019-2020 | 03 Initial Testing Program | |
N0281006
Operating and Historic Float Plane Bases - APEC 16 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0281007
Drums in Watson Lake - APEC 5 |
Confirmatory sampling completed. No further action required. | 2022-2023 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N0281008
Former USTs (Maintenance Garage and Hangar) - APEC 6 |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0281010
Former Tenant-Owned Fuel Underground Storage Tank - APEC 9 |
Initial testing completed. No further action required. | 2020-2021 | 03 Initial Testing Program | |
N0281012
Historic Military Base - APEC 22 |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0281014
Historic Sanitary Sewers and Lagoon - APEC 15 |
Initial testing completed. No further action required. | 2012-2013 | 03 Initial Testing Program | |
N0281015
Historic Military Base - APEC 23 |
Initial testing completed. No further action required. | 2021-2022 | 03 Initial Testing Program | |
N0281016
Historic Tank Farm - APEC 32 |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0281017
Historic Fuel Pipeline - APEC 31 |
Initial testing completed. No further action required. | 2020-2021 | 03 Initial Testing Program | |
N0281018
Operating Automobile Fuelling Station - APEC 19 |
Initial testing completed. No further action required. | 2021-2022 | 03 Initial Testing Program | |
N0281019
Operating INAC Air Tanker Base - APEC 26 |
Initial testing completed. No further action required. | 2022-2023 | 03 Initial Testing Program | |
N0281020
Former Drum Dump - APEC 25 |
Initial testing completed. No further action required. | 2020-2021 | 03 Initial Testing Program | |
N0281022
Historic Borrow Pit with Dump - APEC 27 |
Initial testing completed. No further action required. | 2013-2014 | 03 Initial Testing Program | |
N0285001
Nitchequon |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
- Version:
- 40