Search Results

Search Results Summary
Criteria:
  • Limited to Active Sites
  • Contaminant/Media Pair: PHCs (petroleum hydrocarbons) / Surface soil
  • Reporting Organization: Transport Canada
Select Additional Criteria...
Sort Key:FCSI Identifier (descending)
Sites Found:9
Alternate Views
Choose an alternate view: Map XML CSV Financials Report
Results View Options

Results by Site Impact

Change results view to: Name and Location Contaminants and Media

FCSI Identifier
Site Name
Status Fiscal Year Classification Highest Step Completed
00022894
Eastmain airport land
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00024084
Saint-Augustin port facility
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00026133
Chevery airport (full site)
Detailed testing completed. Remediation / risk management planned. 2023-2024 3 Low Priority for Action 05 Detailed Testing Program
00027709
Kuujjuaq - Asphalt barrels site
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
05031002
C.T.M.A garage
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
05031003
Site portuaire de CAM - quai des traversiers
Detailed testing completed. Remedial action plan under development. 2023-2024 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
09820016
PIN 614306
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
09820041
PIN 614538 - AEC #1 & AEC #2
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
28744001
Chevery airport
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy