Search Results

Search Results Summary
Criteria:
  • Limited to Active Sites
  • Contaminant/Media Pair: PHCs (petroleum hydrocarbons) / Not Available
  • Reporting Organization: Transport Canada
Select Additional Criteria...
Sort Key:FCSI Identifier (ascending)
Sites Found:45
Alternate Views
Choose an alternate view: Map XML CSV Financials Report
Results View Options

Results by Site Impact

Change results view to: Name and Location Contaminants and Media

FCSI Identifier
Site Name
Status Fiscal Year Classification Highest Step Completed
00967003
Fire Training Area
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00967005
Waste Material and Barrel Site
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00967016
Former Gas Station Site
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00967059
Former Remote Radar Site
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
01831001
Otter Creek Former Landfill / Asphalt Plant
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
03875003
Fire Training Area
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
04086002
Fire Training Area
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
05031004
Sediments around wharf
Detailed testing completed. Remediation / risk management planned. 2023-2024 2 Medium Priority for Action 05 Detailed Testing Program
08134003
Former dumps
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
08708005
Bulk fuel storage facility (Esso Tank Farm) - Ottawa Macdonald-Cartier International Airport
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
08708007
Building T107 (Shell Tank Farm) - Ottawa Macdonald-Cartier International Airport
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
09820002
PIN 614053.2
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
09820004
PIN 614076
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
09820006
PIN 614104.2
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
09820007
PIN 614106
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
09820009
PIN 614120
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
09820011
PIN 614132
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
09820020
PIN 614353
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
09820026
PIN 614581
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
09820032
PIN 614070.1
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
09820033
PIN 614458
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
09820035
PIN 614142
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
09820039
PIN 614635
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
09820040
PIN 614547
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
10855006
Metal-clad building - London Airport
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
11867001
SSM Harbour Bed
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
11943002
Thunder Bay Hangar (NOASARA)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
11943003
Waste oil tank - (Former Confederation College, Paipoonge Hangar)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
11943004
Waste oil tank #2 (Bearskin Airlines)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
11943007
Underground storage tanks (Former AVIS)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
11943008
Waste Oil Tank #3 (Thunder Bay Flying School)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
N0002001
Old Fire Training Area
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
N0002003
Southern Fuel Distribution Lines
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
N0002006
Valve Chamber 16
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
N0002013
Building T5
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
N0011003
Fire Training Area
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
N0013001
Fire Training Area
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
N0014002
Fire Training Area
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
N0017001
Fire Training Area
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
N0017003
Old Landfill/Main Drum Cache
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
N0090002
Zone 1 & 2 Area North of Graving Dock
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
N0281008
Former USTs (Maintenance Garage and Hangar) - APEC 6
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
N0281012
Historic Military Base - APEC 22
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
N0281016
Historic Tank Farm - APEC 32
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
N0285001
Nitchequon
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting