  • Contaminant/Media Pair: PHCs (petroleum hydrocarbons) / Soil
  • Contaminant Type: PCBs (Polychlorinated Biphenyl) and PCDD/Fs (polychlorinated dibenzo-p-dioxin/dibenzofuran)
Select Additional Criteria...
Sort Key:FCSI Identifier (ascending)
Sites Found:162
Alternate Views
Choose an alternate view: Map XML CSV Financials Report
Results View Options

Results by Site Impact

Change results view to: Name and Location Contaminants and Media

FCSI Identifier
Site Name
Status Fiscal Year Classification Highest Step Completed
00000903
Parcel 1
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00000949
CAM-4 SRR (Pelly Bay, Nunavut Territory)- Site Summit
Remediation / risk management completed. No further action required. 2017-2018 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00000989
Golf Course - landfill
Initial testing completed. No further action required. 2015-2016 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00000994
Pesticide Container Landfill and Asphalt Dump
Initial testing completed. No further action required. 2015-2016   03 Initial Testing Program
00004105
243 - Kashechewan - 06258 - FORT ALBANY NO. 67 - 0402431305
Historical review completed. No further action required. 2011-2012   02 Historical Review
00006221
633 - Quatsino - 07077 - GRASS POINT 13 - 7000012794
Historical review completed. Initial testing underway. 2023-2024   02 Historical Review
00006315
182 - Constance Lake - 06294 - CONSTANCE LAKE 92 / 3000030495
Detailed testing completed. No further action required. 2012-2013 I Insufficient Information 05 Detailed Testing Program
00006451
648 - Snuneymuxw First Nation - 06816 - NANAIMO RIVER 2 - 0901876304
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00006526
182 - Constance Lake - 06294 - CONSTANCE LAKE 92 / 3000072096
Detailed testing completed. No further action required. 2012-2013 2 Medium Priority for Action 05 Detailed Testing Program
00006600
70 - Mohawks of Kahnawá:ke - 06097 - KAHNAWAKE NO.14 - 2000007593
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00006781
596 - Osoyoos - 07395 - OSOYOOS 1 - 0903043106
Historical review planned. 2023-2024   01 Identify Suspect Sites
00006889
555 - Squamish - 00009 - KITSILANO NO. 6 - 0901112102
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00007686
555 - Squamish - 07968 - SEYMOUR CREEK 2 / 0904441709
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00007899
630 - Mowachaht/Muchalaht - 07044 - AHAMINAQUUS 12 - BC04792810
Detailed testing completed. Remediation / risk management planned. 2023-2024 1 High Priority for Action 05 Detailed Testing Program
00008356
Camp Hughes
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008368
Groundwater-monitoring perimeter - DND RTA/Shannon limit
Initial testing completed. No further action required. 2017-2018   03 Initial Testing Program
00008372
LAB-1, Cape Kakkiviak, SRR Site
Initial testing completed. No further action required. 2017-2018 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008387
Denison Armoury
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00008433
YA-5 Yarrows B - Lot Parking and Roads
Confirmatory sampling completed. No further action required. 2022-2023 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008448
Sudbury Armoury
Detailed testing completed. No further action required. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00008452
Parc Lemay (former dump)
Confirmatory sampling completed. No further action required. 2017-2018 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008458
YA-6 Yarrows Consolidatn Area Y-Gate
Confirmatory sampling completed. No further action required. 2022-2023 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008494
CAM-1A
Detailed testing completed. No further action required. 2017-2018 N Not a Priority for Action 05 Detailed Testing Program
00008550
PIN-1BG Croker River
Initial testing completed. No further action required. 2017-2018   03 Initial Testing Program
00008574
Aurora Armoury
Initial testing completed. No further action required. 2018-2019 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008612
DY-28 Dockyard Signal Hill Bldg 506 - Fmr Oil & Paint Stores
Initial testing completed. No further action required. 2018-2019   03 Initial Testing Program
00008633
DY-16 Dockyard IL Dry Dock - Former subsite DY-4h
Confirmatory sampling completed. No further action required. 2018-2019 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008650
COL-31 Colwood Bldg 65
Detailed testing completed. Remedial action plan under development. 2023-2024 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00008659
COL-40 Colwood North Western Bank of Dunn's Nook
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00008661
BAR-1, Komakuk Beach
Detailed testing completed. No further action required. 2017-2018 3 Low Priority for Action 05 Detailed Testing Program
00008662
BAR-3, Tuktoyaktuk
Detailed testing completed. No further action required. 2017-2018 3 Low Priority for Action 05 Detailed Testing Program
00008663
BAR-4, Nicholson Peninsula
Initial testing completed. No further action required. 2017-2018 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008664
PIN-1BD, Keats Point
Initial testing completed. No further action required. 2017-2018 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008667
FOX-2, Longstaff Bluff
Initial testing completed. No further action required. 2017-2018 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008674
LAB-6
Initial testing completed. No further action required. 2017-2018 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008676
CAM-CB
Initial testing completed. No further action required. 2017-2018 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008678
CAM-A3A
Initial testing completed. No further action required. 2017-2018 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008679
PIN-EB
Initial testing completed. No further action required. 2017-2018   03 Initial Testing Program
00008680
PIN-DA
Initial testing completed. No further action required. 2017-2018 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008681
PIN-CB
Initial testing completed. No further action required. 2017-2018 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008682
PIN-2A
Initial testing completed. No further action required. 2017-2018 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008685
Encroachment SE Corner of Wainwright RTA
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00012845
Trenton Parking Lot
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00016664
Summerside SAR (No Impacts Identified)
Initial testing completed. No further action required. 2012-2013 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00017963
ALBERTON (NORTHPORT) (No Land Based Impacts)
Initial testing completed. No further action required. 2008-2009 N Not a Priority for Action 03 Initial Testing Program
00017982
LOWER MONTAGUE (BTEX/TPH in Soil, Cadmium, Arsenic, Copper, PAH in Sediment)
Confirmatory sampling completed. No further action required. 2017-2018 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00021044
Pallant Creek Hatchery
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00022940
WHITBY (Historical Inlet (backfilled)/Confined Disposal Facility)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00023357
Former McGee Farm Landfill
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00023553
ENNADAI LAKE
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00024052
Belza Farmhouse
Confirmatory sampling completed. No further action required. 2013-2014 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00024057
Montreal Road Complex ON
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00024389
ESCUMINAC (Dredge Spoil Containment Area)
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00024918
Shearwater Aircraft Burn Area (Site 252)
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00025941
605 - Shuswap Band - 07428 - SHUSWAP - BC04868416
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00026527
572 - Soowahlie - 08051 - SOOWAHLIE 14 - BC04882317
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00027660
Kenow Fire Impacted Areas
Remedial action plan completed. Remediation / risk management underway. 2023-2024 I Insufficient Information 07 Develop Remediation/Risk Management Strategy
00027769
Beak Point
Historical review completed. Initial testing underway. 2023-2024   02 Historical Review
00028068
Consul Irrigation Project
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00028172
Jasper National Park, Snaring Warden Station and Associated Buidlings
Suspected site      
00961001
CFS Leitrim Sludge Pits(Disposal Area)
Detailed testing completed. No further action required. 2022-2023 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
01822018
Canadian Side & Northside
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
01822076
Main Base and Civil Aviation Area
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
01822085
Upper Tank Farm - Fuel Recovery Site (UTF 4000 Series)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
01822087
South Escarpment Landfills (SES 1000 Series)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
01822094
Lower Tank Farm (LTF 2000 Series)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
02717131
Hangar 9, Former Tank 33
Historical review completed. No further action required. 2002-2003   02 Historical Review
02739012
Meadowview Landfill - Aldershot
Long term monitoring completed. No further action required. 2017-2018 N Not a Priority for Action 10 Long-Term Monitoring (Optional)
02739026
Former EME Vehicle Maintenance Garage and Sewer - Aldershot
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
02739056
Alleged Drum Dump Area - Aldershot
Initial testing completed. No further action required. 2015-2016 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
02762001
Newport Corner (3101) - Comp. Tech. Building (B9)
Confirmatory sampling completed. No further action required. 2022-2023 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
02762008
Newport Corner (3108) - Antenna Towers (3)
Initial testing completed. No further action required. 2000-2001 N Not a Priority for Action 03 Initial Testing Program
02861003
Osborne Head (5658) - B301 Septic Field
Initial testing completed. No further action required. 2000-2001   03 Initial Testing Program
02861008
Osborne Head (5663) - Former Transformer Site
Remediation / risk management completed. No further action required. 2017-2018 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
02863011
CFB Shearwater (211) - Landfill 1
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
02863021
Shearwater (221) - Lower Fuel Compound and Firing Range
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02865003
McNabs Island (2603) - APU/Generator Hut (B8)
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
02907004
Disposed - Willow Park (4324) - CE Stores (EY3)*
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
02907005
Disposed - Willow Park (4325) - CE Production Centre (EY5)
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
02907006
Willow Park POL Stores (4323)
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
02919005
Dockyard (1005) - PMQ's and Garage (D77, D78, D79 & D81)
Remediation / risk management completed. No further action required. 2014-2015 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02919010
Dockyard (1010) - Electronics Shop (D20)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
03044015
Disposed -Sandwich Pt.(7301) Fmr Pump house-AST/Transformer
Long term monitoring completed. No further action required. 2014-2015 1 High Priority for Action 10 Long-Term Monitoring (Optional)
03765001
Real Property
Detailed testing completed. No further action required. 2018-2019 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
05020004
642 - Cowichan - 06799 - COWICHAN 1 - 7000019894
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
05020010
642 - Cowichan - 06799 - COWICHAN 1 - 7000019494
Initial testing completed. Detailed testing underway. 2023-2024 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
05042021
688 - Tk'emlúps te Secwépemc - 07173 - KAMLOOPS 1 - 7000070696
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
05053010
674 - Lax Kw'alaams - 07770 - LAX KW'ALAAMS 1 - 7000017394
Initial testing completed. Detailed testing underway. 2023-2024 1 High Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
05082002
661 - Hesquiaht - 06887 - REFUGE COVE 6 - 7000089397
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
05088005
555 - Squamish - 07968 - SEYMOUR CREEK 2 - 7000081896
Detailed testing completed. Remediation / risk management planned. 2023-2024 1 High Priority for Action 05 Detailed Testing Program
05152001
126 - Couchiching First Nation - 06241 - COUCHICHING 16A - 3000014095
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
05198005
70 - Mohawks of Kahnawá:ke - 06097 - KAHNAWAKE NO.14 - 2000007893
Detailed testing completed. Remediation / risk management planned. 2023-2024 1 High Priority for Action 05 Detailed Testing Program
05613001
Mount Apica - north slope
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
06294001
Adminstrative Area-Domaine, Lozeau and Bougainville Islands
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
06872011
Moras Island, Pumping station 
Detailed testing completed. No further action required. 2011-2012 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
07503001
Great Duck Island - Lightstation/Engine Building/Dump-Metals,PH,PAH
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
09401040
Alaska Highway - Steamboat Maintenance Camp
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
09540010
AMDU Landfill Site
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
09540012
8 W Fire Fighting Training Area /Hazardous Materials Storage
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
10352004
Site # 4 Vacant Lands at Lyon's Creek in City of Welland. Directly adjacent to Welland Canal.
Remediation / risk management completed. No further action required. 2016-2017 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
10626002
Niagara-on-the-lake Rifle Range
Confirmatory sampling completed. No further action required. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
10829001
Stony Point (fmr Camp Ipperwash)
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
14976006
Cdn Abandoned Landfill Site (CAL Site)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
15305005
WW II Garbage Dump
Remediation / risk management completed. No further action required. 2015-2016 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
15529002
Riverbend Receiver Site
Confirmatory sampling completed. No further action required. 2022-2023 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
15531016
Building 206 and 208
Confirmatory sampling completed. No further action required. 2015-2016 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
16749001
Former RCAF Transmitter Site (Richmond)
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
17348009
Lot 7: Bridge Street; J-17 Bridge Street East Fill; Bridge Street Centre Fill; Turner Street East Fill; Turner Street South
Confirmatory sampling completed. No further action required. 2017-2018 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
17348018
Lot 15: Captain Jacobsen's Park Fill; Paradise Road Wood Walkway; Filled Walkway North Side of West Bay; Gore Street Fill; Pa
Confirmatory sampling completed. No further action required. 2011-2012 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
17385001
Victoria Base - Storage Yard Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
17966001
Seal Bay Transmitter Site
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
18976001
Power Plant at Det Holberg
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
19118010
650 - Penelakut Tribe - 06823 - PENELAKUT ISLAND 7 - 7000012394
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
20033001
Stokes Point
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
20247016
Alert Main Station Landfill
Long term monitoring completed. No further action required. 2017-2018 1 High Priority for Action 10 Long-Term Monitoring (Optional)
23148001
Contrecoeur landfill
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
29757002
Dry material (former dump for), DRDC-South 
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
29757018
Former stop-butt, DRDC-South (ZIP 3) 
Detailed testing completed. No further action required. 2013-2014 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
29757023
Former waste demolition and dump site (N4-1), DRDC-North 
Detailed testing completed. No further action required. 2011-2012 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
29763002
CFS St Johns(5010) - Emerald Vale Training Centre
Initial testing completed. No further action required. 2000-2001   03 Initial Testing Program
33270001
HMCS Gloucester
Confirmatory sampling completed. No further action required. 2015-2016 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
34337002
VIC-1 HMCS Malahat Waterlot
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
34932001
Surgeon Cove Point - Fuel Storage (DFO 001)
Remediation / risk management completed. No further action required. 2012-2013 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
58321006
Uplands - decommissioned oil filled high voltage cables
Confirmatory sampling completed. No further action required. 2016-2017 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
67590001
Area A (West Wharf) - Centre and North portions were divested to the City of Oshawa in the 2011/12 FY. The South portion rem
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
70069005
Eureka - East Airstrip Landfill
Detailed testing completed. No further action required. 2016-2017 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
C1001001
CAM C - MATHESON POINT
Confirmatory sampling completed. No further action required. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C1002001
CAM D - SIMPSON LAKE
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C1004001
CAM F - Sarcpa Lake
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C1005001
CAPE CHRISTIAN
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C1007001
BAR D - Atkinson Point
Long term monitoring completed. No further action required. 2011-2012 1 High Priority for Action 10 Long-Term Monitoring (Optional)
C1017001
BAF 5 - RESOLUTION ISLAND
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C1019001
FOX A - BRAY ISLAND
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
C1022001
FOX E - DURBAN ISLAND
Confirmatory sampling completed. No further action required. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C1041001
CAM A - STURT POINT
Confirmatory sampling completed. No further action required. 2015-2016 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C1042001
CAM B - HAT ISLAND
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
C1044001
PIN C - BERNARD HARBOUR
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
C1045001
PIN-E Cape Peel
Long term monitoring completed. No further action required. 2015-2016 2 Medium Priority for Action 10 Long-Term Monitoring (Optional)
C7007001
DEW-Line: BAR-1 Komakuk Beach
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7008001
DEW-Line - BAR-2 Shingle Point
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7009001
DEW-Line - BAR-3 Tuktoyaktuk
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7010001
DEW-Line - BAR-4 Nicholson Peninsula
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7011001
DEW-Line - PIN-M Cape Parry
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7012001
DEW-Line - PIN-1 Clinton Point
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7013001
DEW-Line - PIN-2 Cape Young
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
C7014001
DEW-Line - CAM-M Cambridge Bay
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7015001
DEW Line - PIN-4 Byron Bay
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7016001
DEW-Line - PIN-3 Lady Franklin Point
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7017001
DEW-Line - CAM-1 Jenny Lind Island
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7018001
DEW-Line CAM-2 Gladman Point
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7019001
DEW-Line - CAM-4 Pelly Bay
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7020001
DEW-Line - CAM-5 Mackar Inlet
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7021001
DEW-Line - FOX-M Hall Beach
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7022001
DEW-Line-FOX-2 Longstaff Bluff
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7023001
DEW-Line - FOX-3 Dewar Lakes
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7024001
DEW Line FOX-4 Cape Hooper
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7025001
DEW Line-FOX-5 Broughton Island
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7026001
DEW-Line - DYE-M Cape Dyer
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7027001
DEW-Line - CAM-3 Shepherd Bay
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
N7075001
Dome Mountain, RCAF and Camp Sites (5 W)
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
N7081001
BAR-E SRR (Horton River) - Site Summit
Detailed testing completed. No further action required. 2017-2018 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
N7093001
CF-18 Crash Site - A/C 188745 (Aug. 05)