Search Results
Search Results Summary | |
---|---|
Criteria: |
|
Sort Key: | FCSI Identifier (ascending) |
Sites Found: | 27 |
Results by Site Impact
Change results view to: Name and Location Contaminants and Media
FCSI Identifier Site Name |
Status | Fiscal Year | Classification | Highest Step Completed |
---|---|---|---|---|
00008389
9 Wing Heavy Equipment Building Site - Parcel #1 |
Detailed testing completed. No further action required. | 2023-2024 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00018907
Glenwood (Warehouse - DFRP# 00994) |
Detailed testing completed. No further action required. | 2012-2013 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00961001
CFS Leitrim Sludge Pits(Disposal Area) |
Detailed testing completed. No further action required. | 2022-2023 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
00961002
9 Wing 25m Firing Range |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
00961004
Drum Area West of Leitrim |
Confirmatory sampling completed. No further action required. | 2022-2023 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00967001
Waste Disposal Site |
Confirmatory sampling completed. No further action required. | 2020-2021 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00967004
Waste Disposal Site |
Confirmatory sampling completed. No further action required. | 2018-2019 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00967025
Former USAF POL Underground Storage |
Confirmatory sampling completed. No further action required. | 2013-2014 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00967027
Abandoned Waste Materials & RCAF Maintenance Facility |
Detailed testing completed. No further action required. | 2014-2015 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00967035
Former UST Site |
Confirmatory sampling completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00967040
Former Tank Farm |
Initial testing completed. No further action required. | 2013-2014 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00967042
Hanger 22 Fuel Hydrant System |
Detailed testing completed. No further action required. | 2014-2015 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00967043
Fuel Contaminated Site |
Confirmatory sampling completed. No further action required. | 2018-2019 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00978002
9 Wing POL Compound |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00978004
9 Wing B109 Wing Fire Hall |
Detailed testing completed. No further action required. | 2023-2024 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00978011
Bldg 17 MSE Garage |
Remediation / risk management completed. No further action required. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00978013
Bldg 86 Wing Photo |
Initial testing completed. No further action required. | 2001-2002 | 03 Initial Testing Program | |
00978014
9 Wing B107 103 Rescue Unit |
Remediation / risk management completed. No further action required. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00978015
9 Wing FFTA |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00978017
1 Hangar 103 Rescue Unit |
Remediation / risk management completed. No further action required. | 2021-2022 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00978020
9 Wing B115 Former CANEX Site |
Detailed testing completed. No further action required. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00978023
Bldg 19 MSE Stores Quansit Hut |
Confirmatory sampling completed. No further action required. | 2019-2020 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00978024
9 Wing B106 Former CANEX site |
Detailed testing completed. No further action required. | 2023-2024 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00978027
Scrap Compound / Supply Storage Area |
Detailed testing completed. No further action required. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00980001
Old Navy Site - Operations Site |
Detailed testing completed. No further action required. | 2009-2010 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
00980012
Old Navy Site - Shooting Range |
Initial testing completed. No further action required. | 2009-2010 | 03 Initial Testing Program | |
N7074001
Old Navy Site - Old Landfill |
Remediation / risk management completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
- Version:
- 40