Search Results

Search Results Summary
Criteria:
  • Contaminant Type: PAHs (polycyclic aromatic hydrocarbon)
  • Province/Territory: Nunavut
Select Additional Criteria...
Sort Key:FCSI Identifier (ascending)
Sites Found:56
Alternate Views
Choose an alternate view: Map XML CSV Financials Report
Results View Options

Results by Site Impact

Change results view to: Name and Location Contaminants and Media

FCSI Identifier
Site Name
Status Fiscal Year Classification Highest Step Completed
00000258
PIONEER IS. - DEVON IS.
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00000289
LOUGHEED ISLAND - CAPE AHNIGHITO
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00000298
STUPART ISLAND
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00000303
LITTLE POINT
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00000304
CAPE ISACHSEN, ELLEF RINGNES ISLAND
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00000348
COPPERMINE/IMPACT LAKE
Detailed testing completed. Remediation / risk management planned. 2023-2024 2 Medium Priority for Action 05 Detailed Testing Program
00000381
PELLY LAKE
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00000383
AKPATOK ISLAND
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00002497
Burn area
Detailed testing completed. No further action required. 2011-2012 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00002660
Area near Storage Building 42 with the Fuel Line & Metal Pallets
Initial testing completed. No further action required. 2009-2010   03 Initial Testing Program
00002747
Eureka High Arctic Weather Station
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00008328
Fort Conger Historic Site
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00008675
FOX-CA
Detailed testing completed. No further action required. 2017-2018 3 Low Priority for Action 05 Detailed Testing Program
00011450
Resolute Bay (petroleum hydrocarbon spill)
Historical review completed. No further action required. 2009-2010   02 Historical Review
00016339
Coral Harbour MCTS Tx- surrounding structure
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00016412
Ranger Seal Range - Old drum location
Historical review completed. No further action required. 2008-2009 N Not a Priority for Action 02 Historical Review
00016421
Schooner Cove Range - Old drum location
Historical review completed. No further action required. 2008-2009 N Not a Priority for Action 02 Historical Review
00016500
Resolute Bay Research Station - South Camp Lot 4 (Soil and Groundwater around southern structures)
Detailed testing completed. No further action required. 2018-2019 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
00023553
ENNADAI LAKE
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00023972
HOPE BAY MINE - ALBERMIN CORP.
Detailed testing completed. No further action required. 2015-2016 N Not a Priority for Action 05 Detailed Testing Program
00024109
POND INLET (GUY`S BIGHT)
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024167
Bathurst Island - Bent Horn (Cameron Island)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00024257
Bathurst Island - Stokes Range
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
00024258
ROMULUS - PANARCTIC C-42 WELL SITE
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00024260
Lougheed Island - Skybattle Bay
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00024425
Resolute Bay Research Station - South Camp Lot 7
Detailed testing completed. No further action required. 2018-2019 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
00028003
Polar Continental Shelf Project - Resolute, NU (Parcel C)
Detailed testing completed. No further action required. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
05156003
142 - Albany - 06258 - FORT ALBANY 67 / 3000077196
Initial testing completed. No further action required. 2013-2014 1 High Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
07525123
Isachsen High Arctic Weather Station
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
07528121
Hall Beach Upper Air Station
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
20247006
Alert Main Station
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
20247016
Alert Main Station Landfill
Long term monitoring completed. No further action required. 2017-2018 1 High Priority for Action 10 Long-Term Monitoring (Optional)
20247024
Alert Dump # 3
Long term monitoring completed. No further action required. 2017-2018 3 Low Priority for Action 10 Long-Term Monitoring (Optional)
20247042
Sewage Outfall
Long term monitoring completed. No further action required. 2017-2018 2 Medium Priority for Action 10 Long-Term Monitoring (Optional)
20906001
Air Navigation Facility: Receiver
Confirmatory sampling completed. No further action required. 2011-2012 I Insufficient Information 09 Confirmatory Sampling and Final Reporting
20907001
Air Navigation Facility: Transmitter
Confirmatory sampling completed. No further action required. 2011-2012 I Insufficient Information 09 Confirmatory Sampling and Final Reporting
20922001
Air Navigation Facility: Non Directional Beacon
Detailed testing completed. No further action required. 2011-2012 I Insufficient Information 07 Develop Remediation/Risk Management Strategy
23466001
Air Navigation Facility: VHF Omnidirectional Range
Confirmatory sampling completed. No further action required. 2011-2012 I Insufficient Information 09 Confirmatory Sampling and Final Reporting
24261001
House 468
Confirmatory sampling completed. No further action required. 2009-2010 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
24261002
House 470
Confirmatory sampling completed. No further action required. 2009-2010 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
24261003
House 472
Confirmatory sampling completed. No further action required. 2009-2010 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
24265001
Green Row Houses - House 673
Confirmatory sampling completed. No further action required. 2009-2010 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
70069014
Eureka North Apron POL
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
70070001
CAM-M LRR (Cambridge Bay, NU - Landfill)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
C1002001
CAM D - SIMPSON LAKE
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C1041001
CAM A - STURT POINT
Confirmatory sampling completed. No further action required. 2015-2016 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
N0010001
Screening Plant/Boneyard
Confirmatory sampling completed. No further action required. 2012-2013 I Insufficient Information 09 Confirmatory Sampling and Final Reporting
N0010003
Former Tank Farm
Detailed testing completed. No further action required. 2012-2013 I Insufficient Information 07 Develop Remediation/Risk Management Strategy
N0010004
Former AST Location North of T-5.
Confirmatory sampling completed. No further action required. 2012-2013 I Insufficient Information 09 Confirmatory Sampling and Final Reporting
N0015001
Former USAF Tank Farm
Confirmatory sampling completed. No further action required. 2014-2015 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
N0015002
Fire Training Area
Confirmatory sampling completed. No further action required. 2017-2018 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
N0015004
Drum Cache #1
Confirmatory sampling completed. No further action required. 2015-2016 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
N0015005
Bitumen Drum Cache - Iqaluit Airport
Confirmatory sampling completed. No further action required. 2012-2013 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
N0017001
Fire Training Area
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
N0017002
Building #4
Confirmatory sampling completed. No further action required. 2012-2013 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
N0017003
Old Landfill/Main Drum Cache
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy