Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
Name | Audit Type | Status | Completion Date | Electronic Link |
---|---|---|---|---|
Quebec Service Centre | Key financial and administrative controls | Complete | Dec 10, 2009 | http://www.pc.gc.ca/docs/pc/ rpts/rve-par/60/index_e.asp |
Quebec Field Unit | Complete | March 30, 2010 | http://www.pc.gc.ca/docs/pc/ rpts/rve-par/62/index_e.asp |
|
External Relations and Visitor Experience Directorate | Complete | March 30, 2010 | http://www.pc.gc.ca/docs/pc/ rpts/rve-par/63/index_e.asp |
|
Strategy and Plans Directorate | In progress | |||
Jasper Field Unit | In progress | |||
Revenue Management (Phase 1) | Assurance | Complete | June 11, 2009 | http://www.pc.gc.ca/docs/pc/ rpts/rve-par/57/index_e.asp |
Fleet Vehicle / Vessel Management | Assurance | Complete | Dec 10, 2009 | http://www.pc.gc.ca/docs/pc/ rpts/rve-par/59/index_e.asp |
Information Management and Privacy | Assurance | Complete | March 30, 2010 | http://www.pc.gc.ca/docs/pc/ rpts/rve-par/61/index_e.asp |
Follow up of Pay and Benefit Audit (including overtime) | Assurance | Complete | March 30, 2010 | http://www.pc.gc.ca/docs/pc/ rpts/rve-par/64/index_e.asp |
Construction Projects / Economic Action Plan | Assurance | In progress | ||
Revenue Management (Phase 2) - canals | Assurance | In progress | ||
Revenue Management (Phase 2) - others | Assurance | In progress |
Name | Program Activity | Program Type | Status | Completion Date | Electronic Link |
---|---|---|---|---|---|
Evaluation Framework For Visitor Experience | PA4 | Framework | Complete | July 9, 2009 | N/A |
Evaluation Framework for Through Highways Management Program | PA5 | Framework | Complete | July 9, 2009 | N/A |
Evaluation Framework for the Twinning of the Trans-Canada Highway at Banff National Park | PA5 | Framework | Complete | July 9, 2009 | N/A |
Evaluation Framework for National Park Establishment and Expansion | PA1 | Framework | In-progress | N/A | |
Evaluation Framework for National Parks Conservation | PA2 | Framework | In-progress | N/A | |
Evaluation of the Parks Canada Asset Management Program | IS | Evaluation | Complete | August 6, 2009 | http://www.pc.gc.ca/docs/pc/ rpts/ rve-par/58/index_e.asp |
Evaluation of the Visitor Service Offer | PA4 | Evaluation | In-progress | N/A | |
Evaluation of Through Highways Management Program | PA5 | Evaluation | In-progress | N/A | |
Electronic Link to Parks Canada’s Internal Audit and Evaluation Documents: http://www.pc.gc.ca/docs/pc/rpts/rve-par/iap-2009-2010_e.asp |