Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
In March 2009, Environment Canada received Treasury Board approval of its 5-year Investment Plan and Organizational Project Management Capacity Assessment (OPMCA) at a Class 2 Level. The projects noted below were identified to TBS prior to March 2009 when these new authorities came into effect. No additional projects exceeding Environment Canada's Capacity Class Level 2 were initiated within this reporting period.
Project | Original Estimated Total Cost |
Revised Estimated Total Cost |
Actual Cost Total |
2009-2010 | ||||
---|---|---|---|---|---|---|---|---|
Main Estimates |
Planned Spending |
Total Authorities |
Actual | Expected date of close-out |
||||
Program Activity: Environmental Science and Monitoring Program | ||||||||
Supercomputer facility upgrade to electrical and cooling capacity (effective project approval) (project close-out phase) | 6.1 | 6.9 | 6.9 | 1.0 | 1.0 | 1.0 | 1.0 | 2009–2010 |
UPS replacement - Dorval facility (effective project approval) (project implementation phase) | 10.6 | 15.4 | 15.4 | 0.7 | 0.7 | 0.7 | 0.7 | 2012–2013 |
Total Projects | 16.7 | 22.3 | 22.3 | 1.7 | 1.7 | 1.7 | 1.7 | - |
Totals may differ between and within tables due to rounding of figures.