Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
Project | Original Estimated Total Cost ($ millions) |
Revised Estimated Total Cost ($ millions) |
Actual Cost Total ($ millions) |
2010-11 ($ millions) | Expected date of close-out |
|||
---|---|---|---|---|---|---|---|---|
Main Estimates |
Planned Spending |
Total Authorities |
Actual | |||||
Program Activity: National Security | ||||||||
Cyber Security Public Awareness Campaign | $9.4M over 5 years and $1.9 M ongoing | $9.4M over 5 years and $1.9 M ongoing | $507,946 | $0 | $878,435 | $878,435 | $507,946 | Ongoing |
Program Activities: Emergency Management, National Security, Law Enforcement, Crime Prevention | ||||||||
Regional Accommodations Project, Implementation Phase | $5.6M | $1.7M | $1.2M | $1.7M | $1.5M | $1.7M | $1.2M | 2012 |
* Regarding the Cyber Security Public Awareness Campaign, the variance between planned and actual spending in 2010-11 can be attributed to unanticipated delays in the production of creative concepts