Site 00001726 - Harris Dam
-
Status
Initial testing completed. No further action required. -
Site Status
Closed -
Classification
Low Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal activities -
Property Type
Non-Federal (Provincial Government)
Site Location
-
Latitude, Longitude
49.825699, -109.545684 -
Municipality
Maple Creek No. 111, SK -
Federal Electoral District
Cypress Hills--Grasslands
Site Management Strategy
- Risk Management
Contaminant Details
Contamination Estimate
-
Cubic Meters
275
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Soil |
PAHs (polycyclic aromatic hydrocarbon) | Sediment |
PAHs (polycyclic aromatic hydrocarbon) | Soil |
Action Plan
Risk Manage the site until the structures are removed. At that time the impacted soil and sediments will be removed.
Additional Information
AEC 1, 2 and 3-Wooden structures.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 0 |
5 km | 23 |
10 km | 1,197 |
25 km | 2,914 |
50 km | 4,470 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$40,419.50
Financial/Annual Information
2022-2023
Reporting Organization
Agriculture and Agri-Food CanadaInternal Identifier
CS-1Highest Step Completed
04 Pre-Classify contaminated site using the CCME National Classification System (optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
Yes
2021-2022
Reporting Organization
Agriculture and Agri-Food CanadaInternal Identifier
CS-1Highest Step Completed
04 Pre-Classify contaminated site using the CCME National Classification System (optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2020-2021
Reporting Organization
Agriculture and Agri-Food CanadaInternal Identifier
CS-1Highest Step Completed
04 Pre-Classify contaminated site using the CCME National Classification System (optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2019-2020
Reporting Organization
Agriculture and Agri-Food CanadaInternal Identifier
CS-1Highest Step Completed
04 Pre-Classify contaminated site using the CCME National Classification System (optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2018-2019
Reporting Organization
Agriculture and Agri-Food CanadaInternal Identifier
CS-1Highest Step Completed
04 Pre-Classify contaminated site using the CCME National Classification System (optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2017-2018
Reporting Organization
Agriculture and Agri-Food CanadaInternal Identifier
CS-1Highest Step Completed
04 Pre-Classify contaminated site using the CCME National Classification System (optional)Total Assessment Expenditure
$40,419.50Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed