Site 00011162 - Skeena river above Babine river
-
Status
Confirmatory sampling completed. No further action required. -
Site Status
Closed -
Classification
High Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal activities -
Property Type
Non-Federal (Provincial Government)
Site Location
-
Latitude, Longitude
55.7158, -127.6844 -
Municipality
Bulkley-Nechako G, BC -
Federal Electoral District
Skeena--Bulkley Valley
Site Management Strategy
- Remediation
Contaminant Details
Contamination Estimate
-
Cubic Meters
3
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
Metal, metalloid, and organometallic | Soil |
Action Plan
Assessment and remediation of small hydrometric equipment within the hydrometric shelter and soil surrounding the building if found to be contaminated with mercury.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 0 |
5 km | 2 |
10 km | 11 |
25 km | 81 |
50 km | 1,765 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$2,580.54 -
Remediation
$762.11
FCSAP Expenditures
-
Assessment
$2,064.43 -
Remediation
$609.69
Financial/Annual Information
2008-2009
Reporting Organization
Environment and Climate Change CanadaInternal Identifier
00011162Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$2,580.54Total Remediation Expenditure
$762.11Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$2,064.43FCSAP Remediation Expenditure
$609.69FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
1.05 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
Yes
2007-2008
Reporting Organization
Environment and Climate Change CanadaInternal Identifier
00011162Highest Step Completed
03 Initial Testing ProgramTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 41