Site 00024013 - Booth Street East, West of Wellington
-
Status
Classification completed. Remedial action plan under development. -
Site Status
Active -
Classification
Medium Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal Real Property -
Property Type
Federal (DFRP Property Number 25885)
Site Location
-
Latitude, Longitude
45.421277, -75.715162 -
Municipality
Ottawa, ON -
Federal Electoral District
Ottawa Centre
Site Management Strategy
- Periodic Monitoring
- Risk Management
Contaminant Details
Contamination Estimate
-
Hectares
0
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PAHs (polycyclic aromatic hydrocarbon) | Groundwater |
PAHs (polycyclic aromatic hydrocarbon) | Soil |
Metal, metalloid, and organometallic | Soil |
Other organics | Soil |
Other Physical/Chemical (pH, temperature, dissolved solids, turbidity, etc.) | Soil |
Action Plan
Installation of an engineered cap. Periodic monitoring.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 5,759 |
5 km | 223,019 |
10 km | 637,533 |
25 km | 1,218,479 |
50 km | 1,437,169 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$44,806.93
FCSAP Expenditures
-
Assessment
$35,845.55
Financial/Annual Information
2023-2024
Reporting Organization
National Capital CommissionInternal Identifier
460707Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2022-2023
Reporting Organization
National Capital CommissionInternal Identifier
460707Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2021-2022
Reporting Organization
National Capital CommissionInternal Identifier
460707Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2020-2021
Reporting Organization
National Capital CommissionInternal Identifier
460707Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$6,346.21Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$5,076.97FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2019-2020
Reporting Organization
National Capital CommissionInternal Identifier
460707Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$118.25Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$94.60FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2018-2019
Reporting Organization
National Capital CommissionInternal Identifier
460707Highest Step Completed
03 Initial Testing ProgramTotal Assessment Expenditure
$38,342.47Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$30,673.98FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 41