Site 00025819 - Surge Narrows Public Port Facility
-
Status
Confirmatory sampling completed. No further action required. -
Site Status
Closed -
Classification
Medium Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Contractual obligation -
Property Type
Non-Federal (Provincial Government)
Site Location
-
Latitude, Longitude
50.226944, -125.112222 -
Municipality
Strathcona C, BC -
Federal Electoral District
North Island--Powell River
Site Management Strategy
- Remediation
Contaminant Details
Contamination Estimate
-
Tons
70
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
BTEXs (benzene, toluene, ethylbenzene, and xylene) | Sediment |
PAHs (polycyclic aromatic hydrocarbon) | Sediment |
Metal, metalloid, and organometallic | Sediment |
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 0 |
5 km | 32 |
10 km | 275 |
25 km | 13,138 |
50 km | 121,444 |
Summary of Annually Reported Data
Total Expenditures
-
Remediation
$193,772.81
Financial/Annual Information
2014-2015
Reporting Organization
Transport CanadaInternal Identifier
00025819Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$193,772.81Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
119 tClosed
Yes
2013-2014
Reporting Organization
Transport CanadaInternal Identifier
00025819Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed