Site 00028047 - Yakoun River near Port Clements
-
Status
Remedial action plan completed. Remediation / risk management underway. -
Site Status
Active -
Classification
High Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal Real Property -
Property Type
Federal (DFRP Property Number 28179)
Site Location
-
Latitude, Longitude
53.613889, -132.20972 -
Municipality
North Coast D, BC -
Federal Electoral District
Skeena--Bulkley Valley
Site Management Strategy
- Remediation
Contaminant Details
Contamination Estimate
-
Cubic Meters
2
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PAHs (polycyclic aromatic hydrocarbon) | Sediment |
PAHs (polycyclic aromatic hydrocarbon) | Soil |
Metal, metalloid, and organometallic | Sediment |
Metal, metalloid, and organometallic | Soil |
Action Plan
Decommission hydrometric station and remove contaminated soil and sediment.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 0 |
5 km | 7 |
10 km | 384 |
25 km | 649 |
50 km | 6,066 |
Summary of Annually Reported Data
Total Expenditures
-
Remediation
$4,573.15
FCSAP Expenditures
-
Remediation
$3,887.18
Financial/Annual Information
2023-2024
Reporting Organization
Environment and Climate Change CanadaInternal Identifier
08OA002Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$4,573.15Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$3,887.18FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2022-2023
Reporting Organization
Environment and Climate Change CanadaInternal Identifier
08OA002Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 41