Site 11022081 - Domestic Waste Landfill #4; Closed
-
Status
Remediation / risk management completed. No further action required. -
Site Status
Closed -
Classification
Low Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal Real Property -
Property Type
Federal (DFRP Property Number 11022)
Site Location
-
Latitude, Longitude
44.275174, -79.88678 -
Municipality
Essa, ON -
Federal Electoral District
Simcoe--Grey
Site Management Strategy
- Risk Management
Contaminant Details
Contamination Estimate
-
Cubic Meters
112,500
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PAHs (polycyclic aromatic hydrocarbon) | Groundwater |
Metal, metalloid, and organometallic | Surface water |
Metal, metalloid, and organometallic | Groundwater |
Metal, metalloid, and organometallic | Soil |
Other inorganics | Groundwater |
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 480 |
5 km | 6,556 |
10 km | 21,222 |
25 km | 245,622 |
50 km | 1,066,330 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$59,371.54 -
Remediation
$205,733.49
FCSAP Expenditures
-
Remediation
$39,199.57
Financial/Annual Information
- 2021-2022
- 2020-2021
- 2019-2020
- 2018-2019
- 2017-2018
- 2016-2017
- 2015-2016
- 2014-2015
- 2010-2011
- 2009-2010
- 2008-2009
- 2007-2008
- 2006-2007
- 2005-2006
2021-2022
Reporting Organization
National DefenceInternal Identifier
0025-C094Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$191.38Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
Yes
2020-2021
Reporting Organization
National DefenceInternal Identifier
0025-C094Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2019-2020
Reporting Organization
National DefenceInternal Identifier
0025-C094Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2018-2019
Reporting Organization
National DefenceInternal Identifier
0025-C094Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$61,939.23Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2017-2018
Reporting Organization
National DefenceInternal Identifier
0025-C094Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$39,199.57Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$39,199.57FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2016-2017
Reporting Organization
National DefenceInternal Identifier
0025-C094Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$56,303.31Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2015-2016
Reporting Organization
National DefenceInternal Identifier
0025-C094Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$48,100.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2014-2015
Reporting Organization
National DefenceInternal Identifier
0025-C094Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$59,086.54Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
Yes
2010-2011
Reporting Organization
National DefenceInternal Identifier
S9421Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
Yes
2009-2010
Reporting Organization
National DefenceInternal Identifier
S9421Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2008-2009
Reporting Organization
National DefenceInternal Identifier
S9421Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2007-2008
Reporting Organization
National DefenceInternal Identifier
S9421Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$285.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2006-2007
Reporting Organization
National DefenceInternal Identifier
S9421Highest Step Completed
03 Initial Testing ProgramTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2005-2006
Reporting Organization
National DefenceInternal Identifier
S9421Highest Step Completed
03 Initial Testing ProgramTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 40