Site 23600001 - Tadoule Lake

  • Status

    Detailed testing completed. No further action required.
  • Site Status

    Closed
  • Classification

    Medium Priority for Action

Site Details

  • Reporting Organization

  • Reason for Involvement

    A reserve as defined in the Indian Act
  • Property Type

    Canada Lands

Site Location

Locate this site on map
  • Latitude, Longitude

    58.71488, -98.48764
  • Municipality

    Churchill 1, MB
  • Federal Electoral District

    Churchill--Keewatinook Aski

Site Management Strategy

  • Additional assessment

Contaminant Details

Contamination Estimate

  • Cubic Meters

    100

The following contaminated media was identified on the site:

Contaminant Type Medium Type
PHCs (petroleum hydrocarbons) Soil

Action Plan

In 2005, heavy fuel stains were reported in the vicinity of the new aboveground storage tanks. An environmental site assessment (ESA) was deemed necessary to determine the extent of the contamination. Previously localized soil contamination (100 m3) in the vicinity of the aboveground storage tanks located at the Nursing Station was remediated in 2001 by Health Canada. A Phase II/III ESA was conducted in 2007/08. The ESA identified petroleum hydrocarbon contamination in four areas. Excavation was recommended for Area 4. Subsurface investigation was recommended for the other 3 areas to determine the best approach to remediation.

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km310
5 km324
10 km324
25 km324
50 km324

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $142,174.00
  • Remediation

    $74,000.00

FCSAP Expenditures

  • Assessment

    $42,800.00

Financial/Annual Information

2009-2010

  • Reporting Organization

    Health Canada
  • Internal Identifier

    303-TL-01
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $74,000.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    100 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2008-2009

  • Reporting Organization

    Health Canada
  • Internal Identifier

    303-TL-01
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $88,674.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    100 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2007-2008

  • Reporting Organization

    Health Canada
  • Internal Identifier

    303-TL-01
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $53,500.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $42,800.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2006-2007

  • Reporting Organization

    Health Canada
  • Internal Identifier

    303-TL-01
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2005-2006

  • Reporting Organization

    Health Canada
  • Internal Identifier

    303-TL-01
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No