Site 54097001 - Lionel Chevrier Building
-
Status
Remediation / risk management completed. No further action required. -
Site Status
Closed -
Classification
Not a Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Contractual obligation -
Property Type
Non-Federal (Non-Agent Crown Corporation)
Site Location
-
Latitude, Longitude
45.01684, -74.72356 -
Municipality
Cornwall, ON -
Federal Electoral District
Stormont--Dundas--South Glengarry
Site Management Strategy
- Additional assessment
- Assessment
Contaminant Details
Contamination Estimate
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Not Available |
PAHs (polycyclic aromatic hydrocarbon) | Not Available |
Metal, metalloid, and organometallic | Not Available |
Action Plan
Based on recommendations of the PQRA, a Risk Management Plan was developed for the site which outlines the recommendation to maintain existing surface barriers and employ administrative controls (in the form of a H&S plan and Soil management plan) to mitigate any risk to exposure of identified COC on-site.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 6,847 |
5 km | 48,994 |
10 km | 58,159 |
25 km | 83,265 |
50 km | 201,906 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$117,496.79
Financial/Annual Information
2017-2018
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 54097001Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
Yes
2016-2017
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 54097001Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$117,496.79Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2011-2012
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 54097001Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
Yes
2010-2011
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 54097001Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
Yes
2009-2010
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 54097001Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2008-2009
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 54097001Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2007-2008
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 54097001Highest Step Completed
04 Pre-Classify contaminated site using the CCME National Classification System (optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2006-2007
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 54097001Highest Step Completed
04 Pre-Classify contaminated site using the CCME National Classification System (optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2005-2006
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 54097001Highest Step Completed
04 Pre-Classify contaminated site using the CCME National Classification System (optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 40