Site N0032004 - Dumpsite U - Former borrow pit
-
Status
Confirmatory sampling completed. No further action required. -
Site Status
Closed -
Classification
High Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal activities -
Property Type
Non-Federal (Municipal Government)
Site Location
-
Latitude, Longitude
49.073056, -125.78 -
Municipality
Alberni-Clayoquot C, BC -
Federal Electoral District
Courtenay--Alberni
Contaminant Details
Contamination Estimate
-
Cubic Meters
1,887
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
Metal, metalloid, and organometallic | Surface water |
Metal, metalloid, and organometallic | Groundwater |
Metal, metalloid, and organometallic | Sediment |
Action Plan
Monitoring ongoing
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 94 |
5 km | 109 |
10 km | 1,306 |
25 km | 6,689 |
50 km | 8,285 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$118,346.77 -
Remediation
$100,277.08
FCSAP Expenditures
-
Remediation
$12,482.00
Financial/Annual Information
2013-2014
Reporting Organization
Transport CanadaInternal Identifier
N0032004Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
Yes
2012-2013
Reporting Organization
Transport CanadaInternal Identifier
N0032004Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2011-2012
Reporting Organization
Transport CanadaInternal Identifier
N0032004Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2010-2011
Reporting Organization
Transport CanadaInternal Identifier
N0032004Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2009-2010
Reporting Organization
Transport CanadaInternal Identifier
N0032004Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$14,470.93Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$12,482.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2008-2009
Reporting Organization
Transport CanadaInternal Identifier
N0032004Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$20,722.80Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2007-2008
Reporting Organization
Transport CanadaInternal Identifier
N0032004Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$41,263.42Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2006-2007
Reporting Organization
Transport CanadaInternal Identifier
N0032004Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$65,083.35Total Remediation Expenditure
$65,083.35Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2005-2006
Reporting Organization
Transport CanadaInternal Identifier
N0032004Highest Step Completed
04 Pre-Classify contaminated site using the CCME National Classification System (optional)Total Assessment Expenditure
$12,000.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 40