Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
The following table lists the internal audit work expected to be completed during fiscal year 2009-2010, as well provides an indication of the internal audit work tentatively planned for initiation in fiscal year 2009-2010. Completed audit reports, which include management action plan to address audit recommendations, are posted at the following link: <http://www.crs-csex.forces.gc.ca/reports-rapports/index-eng.asp>.
Name of Internal Audit | Internal Audit Type | Status | Expected Completion Date |
---|---|---|---|
Inventory Management: Surpluses and Disposal | Assurance | In Progress | 1st Quarter 2009-2010 |
Canadian Forces Housing Agency | Assurance | In Progress | 1st Quarter 2009-2010 |
HR Service Delivery | Review | In Progress | 1st Quarter 2009-2010 |
CP140 Aurora Maintenance Contracts | Management Action Plan Follow-Up | In Progress | 1st Quarter 2009-2010 |
Revenue Management | Assurance | In Progress | 1st Quarter 2009-2010 |
Risk Analysis of Contracts | Risk Analysis | In Progress | 1st Quarter 2009-2010 |
Audit of Security Incident Management | Assurance | In Progress | 2nd Quarter 2009-2010 |
Minor Warships and Auxiliary Vessel In-Service Support Contract | Assurance | In Progress | 2nd Quarter 2009-2010 |
Information Management Projects | Risk Analysis | In Progress | 2nd Quarter 2009-2010 |
CRS Audit Perspective 2008 | Assurance | In Progress | 2nd Quarter 2009-2010 |
Implementation of Modern Management | Assurance | In Progress | 3rd Quarter 2009-2010 |
Contracting for Professional and Technical Services | Management Action Plan Follow-Up | In Progress | 3rd Quarter 2009-2010 |
FMF Cape Breton Shop Consolidation Project | Assurance | In Progress | 4th Quarter 2009-2010 |
Unexploded Ordnance Liability | Assurance | In Progress | 4th Quarter 2009-2010 |
Leave and Absence Administration | Assurance | In Progress | 4th Quarter 2009-2010 |
RMC Kingston | Assurance | Planned | 2010-2011 |
IT Asset Management | Management Action Plan Follow-Up |
Planned (see note) |
2010-2011 |
Security Program Management | Assurance |
Planned (see note) |
2010-2011 |
Joint Support Ship | Assurance |
Planned (see note) |
2010-2011 |
Financial Management Practices – Selected Operational Units | Assurance |
Planned (see note) |
2010-2011 |
Delegation of Financial Authorities | Assurance |
Planned (see note) |
2010-2011 |
Canadian Forces Pension Plan | Assurance |
Planned (see note) |
2010-2011 |
Business Continuity Planning | Assurance |
Planned (see note) |
2010-2011 |
CRS Audit Perspective 2009 | Assurance | Planned | 2010-2011 |
Halifax Class Modernization/Frigate Life Extension (FELEX) | Assurance |
Planned (see note) |
2011-2012 |
Note: