This page has been archived.
Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
Description | The Mid-Shore Patrol Vessels (MSPV) project will acquire up to 9 Mid-Shore Patrol Vessels for the Canadian Coast Guard (CCG) Fleet - five of the nine MSPV will be used primarily to support the Conservation and Protection Program in the Maritimes, Quebec and Pacific Regions. The other four vessels will be used in a joint program with the Royal Canadian Mounted Police (RCMP) to enhance maritime security along the Great Lakes – St. Lawrence Seaway system. This project serves two purposes:
|
||
---|---|---|---|
Project Phase | The MSPV Project is currently in the Construction phase. | ||
Lead Department | Canadian Coast Guard, Fisheries and Oceans Canada | ||
Contracting Authority | Public Works and Government Services Canada | ||
Participating Departments | Industry Canada; RCMP; Treasury Board Secretariat; Privy Council Office; Indian and Northern Affairs Canada; Atlantic Canada Opportunities Agency; Western Economic Diversification Canada; Canadian Economic Development; Finance Canada; Public Safety Canada; Department of National Defence. | ||
Prime Contractor | Irving Shipbuilding Inc. |
||
Major Sub-Contractor(s) | International Contract Engineering, Damen, Lloyd’s Register, MTU. | ||
Project Outcomes | The MSPV project supports the Vessel Procurement and Fleet Renewal objectives of the Canadian Coast Guard. Project Outcomes are the measurable results expected at the end of the project and contribute to the Fleet Operational Readiness Program Activity in the DFO Program Activity Architecture. |
||
Progress Report and Explanations of Variance |
All 2009-10 objectives for the MSPV project were achieved. In August 2009, a contract was awarded to Irving Shipbuilding Inc. for the procurement of 9 MSPV. Construction of the first vessel began in September 2010 and delivery is expected in Fall 2011. |
||
Industrial Benefits | Canadian industry will benefit from this project. The Request for Proposal (RFP) requires overall industrial benefits equal to 100% of contract value. Regional allocation of industrial benefits is monitored by Industry Canada. |
Major Milestones | Date |
---|---|
Preliminary Project Approval | August 2005 |
Effective Project Approval | June 2006 |
1st Request for Proposal (RFP) (cancelled) | July 2007 |
Amended Effective Project Approval – to include 4 additional vessels identified in Budget 2007 | December 2007 |
2nd RFP issued (cancelled) | August 2008 |
3rd RFP issued | March 2009 |
Contract Awarded | August 2009 |
First Vessel Delivery | Fall 2011 |
Delivery of final MSPV | Summer 2013 |
Current Estimated Total Expenditure |
Forecast Expenditures to March 31, 2010 |
Planned Spending 2010-11 |
Future Years' Requirements |
---|---|---|---|
227.0 | 57.0 | 85.1 | 84.9 |
Description | The Offshore Fisheries Science Vessels (OFSV) project will acquire three OFSV for the Canadian Coast Guard (CCG) Fleet. The OFSV will replace four aging Coast Guard ships on the east and west coasts of Canada that provide a platform from which critical scientific research and ecosystem-based management can be performed. |
||
---|---|---|---|
Project Phase | The OFSV Project is currently in the design phase. | ||
Lead Department or Agency | Canadian Coast Guard, Fisheries and Oceans Canada | ||
Contracting Authority | Public Works and Government Services Canada | ||
Participating Departments or Agencies | Industry Canada; Treasury Board Secretariat; Privy Council Office; Indian and Northern Affairs Canada; Atlantic Canada Opportunities Agency; Western Economic Diversification Canada; Canadian Economic Development; Finance Canada. | ||
Prime Contractor | To be determined |
||
Major Sub-Contractor(s) | Design Contractor: STX Canada Marine Inc. | ||
Project Outcomes | The OFSV project supports the Vessel Procurement and Fleet Renewal objectives of the Canadian Coast Guard. Project Outcomes are the measurable results expected at the end of the project and contribute to the Fleet Operational Readiness Activity in the DFO Program Activity Architecture. |
||
Progress Report and Explanations of Variance | During 2009-10, the concept design work was finalized and the associated Design Instructions and Guidance were developed. An RFP for design was issued in March 2010 and the design contract was awarded in October 2010. The Preliminary Project Approval was amended in September 2010, to extend the design phase, and separate the design contract from the eventual construction contract. This approach was adopted to increase project management efficiencies within the approved funding envelope and account for the implementation of the National Shipbuilding Procurement Strategy under which the OOSV will be constructed. Project milestones have been revised and the vessel is expected to be delivered by 2014. |
||
Industrial Benefits | Canadian industry will benefit from this project. Regional distribution will be determined at contract award. |
Major Milestones | Date |
---|---|
Preliminary Project Approval | October 2005 |
Amended Preliminary Project Approval | November 2006 |
2nd Amended Preliminary Project Approval – to include 4 additional vessels identified in Budget 2007 | June 2009 |
Issue RFP for Design | Spring 2010 |
3rd Amended Preliminary Project Approval – to award contract | September 2010 |
Issue Design Contract | October 2010
|
Commence Process to obtain Effective Project Approval and Authority to Contract | Fall 2011 |
Construction Contract Award | Winter 2012 |
First Vessel Delivery | April 2014 |
Delivery of final OFSV | Winter 2015 |
Current Estimated Total Expenditure |
Forecast Expenditures to March 31, 2010 |
Planned Spending 2010-11 |
Future Years' Requirements |
---|---|---|---|
244.0 | 7.4 | 5.2 | 231.4 |
Description | The Offshore Oceanographic Science Vessel (OOSV) project will acquire a replacement vessel for the Canadian Coast Guard's largest science vessel - CCGS Hudson. This vessel was built in 1963 and its replacement is critical to fulfilment of the Department's science mandate as well as mandates of other government departments and agencies. The vessel currently operates on the east coast of Canada. |
||
---|---|---|---|
Project Phase | The OOSV Project is currently in the design phase. | ||
Lead Department or Agency | Canadian Coast Guard, Fisheries and Oceans Canada | ||
Contracting Authority | Public Works and Government Services Canada | ||
Participating Departments or Agencies | Industry Canada; Environment Canada; Natural Resources Canada; Treasury Board Secretariat; Privy Council Office; Indian and Northern Affairs Canada; Atlantic Canada Opportunities Agency; Western Economic Diversification Canada; Canadian Economic Development; Finance Canada. | ||
Prime Contractor | To be determined |
||
Major Sub-Contractor(s) | Design Contractor: STX Canada Marine Inc. | ||
Project Outcomes | The OOSV project supports the Vessel Procurement and Fleet Renewal Objectives of the Canadian Coast Guard. Project Outcomes are the measurable results expected at the end of the project and contribute to the Fleet Operational Readiness Program Activity in the DFO Program Activity Architecture. |
||
Progress Report and Explanations of Variance | During 2009-10, the concept design work was finalized and the Work Scope definition and the associated Design Instructions and Guidance were developed. An RFP for design was issued in April 2010 and the design Contract was awarded in October 2010. The Preliminary Project Approval was amended in September 2010, to extend the design phase, and separate the design contract from the eventual construction contract. This approach was adopted to increase project management efficiencies within the approved funding envelope and account for the implementation of the National Shipbuilding Procurement Strategy under which the OOSV will be constructed. Project milestones have been revised and the vessel is expected to be delivered by 2015. |
||
Industrial Benefits | Canadian industry will benefit from this project. Regional distribution will be determined at contract award. |
Major Milestones | Date |
---|---|
Preliminary Project Approval | July 2008 |
1st Amended Preliminary Project Approval | June 2009
|
Issue RFP for design | Spring 2010 |
2nd Amended Preliminary Project Approval – to award contract | September 2010 |
Issue Design Contract | October 2010 |
Commence process to obtain Effective Project Approval and Authority to Contract | Fall 2011 |
Construction Contract Award | Spring 2012 |
Delivery of OOSV | June 2014 |
Current Estimated Total Expenditure |
Forecast Expenditures to March 31, 2010 |
Planned Spending 2010-11 |
Future Years' Requirements |
---|---|---|---|
144.4 | 5.1 | 4.1 | 135.2 |
Description | The new Polar Icebreaker is expected to be delivered in time for the decommissioning of the CCGS Louis S. St-Laurent. This new polar icebreaker will help strengthen Canada's Arctic sovereignty and will be able to operate in the Arctic in more severe weather conditions and for a longer period of time - 3 seasons instead of the current 2 seasons. |
||
---|---|---|---|
Project Phase | The Polar Icebreaker Project is currently in the definition phase. | ||
Lead Department or Agency | Canadian Coast Guard, Fisheries and Oceans Canada | ||
Contracting Authority | Public Works and Government Services Canada | ||
Participating Departments or Agencies | Industry Canada; Treasury Board Secretariat; Privy Council Office; Indian and Northern Affairs Canada; Atlantic Canada Opportunities Agency; Western Economic Diversification Canada; Canadian Economic Development; Finance Canada; Environment Canada; National Defence. | ||
Prime Contractor | To be determined |
||
Major Sub-Contractor(s) | n/a at this time | ||
Project Outcomes | The Polar project supports the Vessel Procurement and Fleet Renewal Objectives of the Canadian Coast Guard. Project Outcomes are the measurable results expected at the end of the project and contribute to the Fleet Operational Readiness Program Activity in the DFO Program Activity Architecture. |
||
Progress Report and Explanations of Variance | In-house conceptual design work in preparation for detailed design work to follow has commenced and is ongoing throughout 2010-11. An RFP for the design portion of the project will be released in Spring 2011 with the winning bidder to be announced in Summer 2011. The detailed design work by the winning design company will commence in 2011 to be delivered in 2013. |
||
Industrial Benefits | Canadian industry will benefit from this project. Regional distribution will be determined at contract award. |
Major Milestones | Date |
---|---|
Approbation définitive de projet | June 2009 |
Design Contract Awards Target Date | 2011
|
Effective Project Approval – Target Date | 2013 |
Contract Award (Construction) | 2013 |
Delivery of Polar Icebreaker | 2017 |
Current Estimated Total Expenditure |
Forecast Expenditures to March 31, 2010 |
Planned Spending 2010-11 |
Future Years' Requirements |
---|---|---|---|
800.0 | 15.8 | 9.5 | 774.7 |