Site 00026090 - Port Hardy Airport AEC 37 Former UST
-
Status
Remedial action plan completed. Remediation / risk management underway. -
Site Status
Active -
Classification
Low Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal Real Property -
Property Type
Federal (DFRP Property Number 18951)
Site Location
-
Latitude, Longitude
50.684444, -127.378611 -
Municipality
Port Hardy, BC -
Federal Electoral District
North Island--Powell River
Site Management Strategy
- Remediation
Contaminant Details
Contamination Estimate
-
Cubic Meters
180
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Soil |
PAHs (polycyclic aromatic hydrocarbon) | Soil |
Action Plan
Soil remediation completed on site. Off-site contamination identified. Delineation of contamination conducted in 2017/18.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 114 |
5 km | 1,051 |
10 km | 4,137 |
25 km | 9,618 |
50 km | 14,548 |
Summary of Annually Reported Data
Total Expenditures
-
Remediation
$206,072.05
FCSAP Expenditures
-
Remediation
$206,072.05
Financial/Annual Information
2023-2024
Reporting Organization
Transport CanadaInternal Identifier
00026090Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2022-2023
Reporting Organization
Transport CanadaInternal Identifier
00026090Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2021-2022
Reporting Organization
Transport CanadaInternal Identifier
00026090Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2020-2021
Reporting Organization
Transport CanadaInternal Identifier
00026090Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2019-2020
Reporting Organization
Transport CanadaInternal Identifier
00026090Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2018-2019
Reporting Organization
Transport CanadaInternal Identifier
00026090Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2017-2018
Reporting Organization
Transport CanadaInternal Identifier
00026090Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$55,000.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$55,000.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
357 tClosed
No
2016-2017
Reporting Organization
Transport CanadaInternal Identifier
00026090Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$151,072.05Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$151,072.05FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
357 tClosed
No
- Version:
- 41