This page has been archived.
Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
This report presents the findings of an evaluation of the Strategic Investment Framework (SIF), which was a fund established to guide investments in implementing the Public Service Modernization Act (PSMA).
The objective of this evaluation was to examine the implementation, relevance and performance (efficiency, effectiveness and economy) of the investments made under the SIF, the extent to which they facilitated achieving outcomes of the PSMA, and the lessons learned from this initiative. The scope of the evaluation focused on the departments that accessed SIF funds, which included central agencies. This evaluation did not assess the effectiveness of the tools or instruments implemented by these departments. Although the SIF was central to the PSMA implementation, this was not an evaluation of the PSMA but of the use of SIF funds.[1]
Between 2004 and 2009 $200 million in SIF funding was provided to 40 departments and agencies to support the achievement of the PSMA's objectives, which were as follows:
The funds were applied to five notional envelopes: institutional change, PSMA human resources (HR) information technology (IT) systems, people preparation, new functions, and project management.
The methodology for the evaluation incorporated the following lines of evidence:
A key feature of this evaluation was that this initiative had ended prior to the evaluation's implementation. As a result, rather than recommendations, lessons learned are presented that could be applied to future funding programs that have a similar design. In addition, the legislative review of the PSMA was undertaken at a later time, during which the environment evolved and, therefore, may have arrived at additional insights and/or conclusions.
A number of limitations, including the timing of the evaluation after the initiative ended, resulted in restrictions on the availability of data to support the evaluation. For instance, the department in which the SIF Project Office was situated was reorganized three times during the life of the initiative, which resulted in the inability to locate many knowledgeable potential informants. This also meant that a survey could not be undertaken.
The SIF appears to have been well implemented, resulting in outputs being created to appropriately guide SIF funding to projects that were consistent with short-term outcomes. There was sufficient evidence for the evaluation to make conclusions on immediate and short-term outcomes but not enough to make conclusions on medium- and long-term outcomes. This should not be interpreted to mean that these outcomes were not achieved, but rather that they could not be measured or assessed based on the available evidence.
SIF-sponsored activities were undertaken throughout departments and agencies to support developing human resources management (HRM) capacity needed to implement the PSMA. The evidence showed that these activities were relevant. In fact, all key informants stated that there remains an ongoing need for the types of activities that were funded by the SIF:
Evaluation questions relating to efficiency focused mainly on how effectively the initiative had been implemented. In this regard, the evaluation results indicate that the SIF was organized and implemented as expected. Ninety-four per cent of SIF funding was disbursed to departments and agencies, and 83.4 per cent of the funds approved were invested by departments and agencies.
Although the Master Plan[2] was issued a year later than the SIF, the first progress report indicated that the PSMA Secretariat developed and maintained project implementation timetables to identify key activities and critical milestones. Status and summary reports were later used to inform the commitments and achievements. Evidence shows that all PSMA legislative requirements were met to a significant degree. There is evidence on the project plan's effectiveness in guiding horizontal initiatives across departments and agencies:
Although results from the document review and from key informant interviews showed that SIF funding did indeed provide value, the evaluation could not determine if this could have been accomplished with fewer resources.
The evidence shows that the level and nature of uptake of SIF funds was appropriate. Eighty-eight per cent of departments and agencies were assisted either directly or indirectly through the Small Agencies Transition Support Team (SATST) or parent departments with their PSMA implementation requirements.
The evaluation could not make a firm conclusion on the extent to which the SIF investment strategy contributed to achieving medium- and long-term outcomes of the PSMA, in part because of a lack of informants and reduced reporting among funding recipients.
Nonetheless, the expected outputs and most immediate and short-term outcomes were achieved. Outputs such as guidelines, communications and training led to the immediate outcomes, thus resulting in departments applying and receiving funding for projects that aligned with PSMA priorities and principles, although the timeliness of implementation was identified as an issue. The short-term outcomes, for the most part, also appear to have been achieved, as evidenced by institutional change[3], HR IT systems, "people preparation" events, and new HR functions to support PSMA implementation. However, the evaluation was unable to draw a conclusion on the extent to which these, in turn, supported public service HR needs, resource processes, cultural change and accountabilities. Similarly, conclusions could not be drawn regarding the long-term outcomes of hiring the right people, collaborative labour–management relations, increased focus on learning and training for employees at all levels, and improved clarity in roles and accountability. These represent a significant limitation of the evaluation.
Many of the lessons learned from this evaluation relate to the issue of performance measurement and reporting. Although the reorganizations of PSHRMAC and the CPSA highlighted the issue of information management, greater awareness is needed regarding the importance of establishing performance measurement strategies and reporting frameworks before implementing government initiatives. Such strategies and frameworks would provide senior management with the information needed on their impact.